In brief
Acceptance in an IT project is the formal confirmation that a delivered system or phase meets the agreed acceptance criteria. Acceptance criteria are measurable conditions a system must satisfy for the customer to accept it: features, performance, security, documentation. They are written before work starts, verified with acceptance testing, and the outcome is recorded in a sign-off report with a list of open defects and fix dates. Without criteria, acceptance turns into a dispute about expectations.
Why acceptance starts at the beginning of the project
Acceptance is the moment many things hinge on at once: payment for a phase, the start of the warranty, the transfer of code ownership and the decision to go live. For a contract for a specific work, the Polish Civil Code states plainly that the customer must accept the work that the contractor delivers in line with its obligation (Article 643). So the question is: in line with what? The answer has to exist before anyone writes the first line of code.
The most common problem is criteria added at the end. The customer sees the system for the first time in acceptance testing and judges it by their own expectations, while the contractor judges it by a specification it reads its own way. Both are right, because nobody wrote down what “works” means.
In a fixed-scope model the acceptance criteria are part of the contract. In a time-based model they play a similar role at the level of tasks and releases. The differences are covered in the article Time and materials or fixed price.
How to write acceptance criteria
A good criterion can be verified with a test, and the result does not depend on who checks it. A comparison:
| Weak criterion | Measurable criterion |
|---|---|
| The system is fast | A customer search by national ID number returns a result in under 1 s at p95 with 200 concurrent users |
| The report is correct | The daily report matches the accounting system's summary to the cent for 30 days of test data |
| The application is secure | No open high or critical vulnerabilities in the penetration test, all OWASP ASVS items at the chosen level verified |
| There is documentation | The deployment guide lets the customer's team set up a test environment without the contractor's help |
| The ERP integration works | An order from the MES appears in the ERP within 5 min, and a connection error goes to a retry queue without losing the order |
It helps to group the criteria: functional (what the system does), non-functional (performance, uptime, security, accessibility for people with disabilities), data (migration, reconciliation) and operational (documentation, monitoring, rollback procedure). How to read response times is covered in the article Percentiles instead of averages.
Functional requirements are easiest to write as examples in a “given… when… then…” format. Such examples are test scenarios from day one, as we describe in the article BDD and acceptance testing.
Definition of Done vs acceptance criteria
In Scrum, the Definition of Done sits alongside acceptance criteria. They are different things:
- Acceptance criteria apply to a single backlog item or phase: what this specific feature must do.
- The Definition of Done applies to all work in the team: code reviewed, automated tests passing, documentation updated, the change deployed to a test environment.
The Scrum Guide says that a backlog item that does not meet the Definition of Done cannot be released or even presented at the Sprint Review, and returns to the Product Backlog. In a project with an external vendor, agree the Definition of Done in writing at the start, because it decides whether the hours billed for a task produced finished work.
Acceptance testing: who, what and when
The ISTQB Foundation Level syllabus lists several forms of acceptance testing: user acceptance testing, operational acceptance testing, contractual and regulatory acceptance testing, and alpha and beta testing. Business IT projects most often involve the first three.
Rules that save time:
- Acceptance testing is run by the customer or an independent team, not the team that built the system. The contractor provides test data, the environment and support with defects. An example is the independent acceptance testing of a regional government e-services system.
- Acceptance scenarios are ready before the system is handed over. The contractor knows them in advance, so it can run them first.
- The acceptance environment resembles production: the same integrations, similar data, the same configuration.
- Testing time is in the schedule, along with time for fixes and retesting.
How to fit acceptance testing into the broader plan is covered in the article Test plan and test strategy.
The sign-off report: what to record
The sign-off report (acceptance protocol) is the document that closes a phase. It should contain:
- the subject of acceptance: phase, system version, release number, list of features;
- the acceptance criteria and the result for each: met, not met, not applicable;
- a list of open defects with their class and fix date;
- the decision: acceptance without reservations, conditional acceptance, or refusal with reasons;
- the items handed over: code, documentation, access credentials, test results;
- the date and signatures of the people authorized in the contract.
Defect classes must be defined in the contract before the first defect appears. A typical split:
| Class | Description | Effect on acceptance |
|---|---|---|
| Blocking | prevents use of a key feature, no workaround | acceptance refused |
| Major | the feature works incorrectly, a workaround exists but is costly | conditional acceptance or refusal, depending on the number |
| Minor | does not affect the process, for example a typo or screen layout | acceptance with a fix date |
Conditional acceptance lets you move on without waiting for minor fixes. The condition: every reservation has a date and an owner, and its fix is verified separately.
Contracts often also set a period for raising comments, after which the phase counts as accepted. That is fair to both sides, provided the period leaves real time for acceptance testing.
Questions and answers
Who should write the acceptance criteria?
The customer, with the contractor's help. The customer knows what the business needs and what the regulatory requirements are. The contractor helps turn them into measurable conditions and flags those that are unrealistic or expensive. The criteria should be approved by the product owner or the person authorized to accept the work, because that person will later sign the report.
Can you refuse acceptance because of a single defect?
Yes, if it is a blocking defect under the classes defined in the contract. For major and minor defects the contract usually provides for conditional acceptance and a fix date. A refusal should come with written reasons that point to the specific acceptance criterion that was not met.
How does phase acceptance differ from final acceptance?
Phase acceptance confirms part of the scope and usually triggers payment for that phase. Final acceptance covers the whole system, often after end-to-end testing and a trial deployment, and starts the warranty and the final transfer of rights. Describe in the contract how defects found at final acceptance in a module accepted earlier are handled, so there is no dispute over whether the warranty covers them.
How long should acceptance testing take?
As long as it takes to run the acceptance scenarios, fix defects and retest. The duration depends on the number of scenarios, integrations and the availability of the business people who test. Base the period in the contract on the number of scenarios rather than a figure set upfront, because a period that is too short ends in acceptance without verification.