The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
The integration between the WMS and warehouse automation is only tested on site, once the installation is ready.
Approach
Warehouse automation emulators let us test the flows (receiving, storage, picking, shipping) before the installation is mounted.
Goal
Full regression time: from days to hours, target ≤ 8 h; Share of automated regression cases: ≥ 70% of critical paths.

Client context

Logistics operators integrate with dozens of customers, carriers, and platforms, and the number of interfaces grows faster than the team that maintains them. This logistics operator is opening a new warehouse with automation (sorters, conveyors) integrated with a WMS.

Challenge

The integration between the WMS and warehouse automation is only tested on site, once the installation is ready. Testing delays push back the opening date.

Requirements and constraints

  • NIS2, that is Directive (EU) 2022/2555, and the amendment to the Polish National Cybersecurity System Act (KSC) require essential and important entities to implement cybersecurity risk management measures, supply chain security, and incident reporting within short deadlines (an early warning within 24 hours). Management is personally accountable, so documenting decisions is part of the product. (source)
  • IEC 62443 (security of industrial automation systems) divides an installation into zones and conduits, defines security levels (SL), and sets requirements for component suppliers. Every IT–OT connection must go through a controlled conduit. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, and every deliverable shipped with documentation that the client's team can take over.

Approach and architecture

Instead of automating everything in manual regression, we select cases using a simple calculation: execution frequency, feature stability, maintenance cost, and risk. Tests are data-independent (each one prepares and cleans up its own data), carry tags that let us run smoke, regression, and nightly suites, and unstable tests go into quarantine instead of blocking releases.

Warehouse automation emulators let us test the flows (receiving, storage, picking, shipping) before the installation is mounted. We automate the end-to-end tests, and on site we only run confirmation tests.

Key elements of the solution:

  • Sorter and conveyor emulators
  • Automated tests of warehouse flows
  • Exception handling tests (jams, missing label)
  • Confirmation tests on the installation

Team and roles

RoleCountResponsibility
QA lead1organizing the testers' work, test case reviews, defect metrics
Test automation engineer2framework, scripts, CI integration
Test analyst (ISTQB)1designing and executing test cases, reporting defects
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Regression audit and selection of candidates1–2automation map, cost-benefit calculation
2. Framework build and CI integration3–6framework, pipeline, test code standard
3. Automation of critical paths7–13smoke and regression suites
4. Stabilization and reporting14–17quality dashboard, quarantine for unstable tests
5. Handover and team training18–20documentation, workshops, maintenance plan

Technology stack

Python, pytest, automation emulators, SQL, Jenkins.

Risks and how we mitigate them

RiskHow we mitigate it
Delays in delivery of hardware and devicessimulators and emulators in tests, earlier orders, HIL tests on prototypes
Test environments unavailable or unstableenvironment booking schedule, virtualization of external services (mocks), daily environment smoke test
Impact of IT changes on production continuity (OT)tests on a rig that reproduces the line, changes only in downtime windows, zones and conduits per IEC 62443

Measurable goals and KPIs

The values below are targets that we agree with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
Full regression timefrom days to hours, target ≤ 8 hsuite execution time in CI
Share of automated regression cases≥ 70% of critical pathstest repository
Critical defects found after go-live0 critical defects in the first 30 daysproduction incident register

Lessons learned and good practices

Automation emulators save the most time, because they move testing ahead of the installation date. Exception handling decides whether the warehouse copes with peak load. Automation pays off when it runs on every change, not once before a release.

Why B2B.net

We combine two models: we supply individual specialists and entire teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the outcome, we work at a fixed price for a defined scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies, and experience with ISO 27001, DORA, and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.

Acceptance criteria

Each phase ends with a formal acceptance against criteria agreed at the start. In this project, acceptance covers: automation map, cost-benefit calculation; framework, pipeline, test code standard; smoke and regression suites; quality dashboard, quarantine for unstable tests; documentation, workshops, maintenance plan. Final acceptance requires a report of the KPI measurement against the baseline, complete documentation handed over to the client's team, and a list of recommendations for the next stage, with the cost and risk of each one assessed.

Next step

If you recognize these problems in your organization, let's start with a short diagnosis: one workshop with your team and written recommendations. Write to us at office@b2bnetwork.pl.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk

B2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.

More projects: Logistics