In brief
An IT vendor exit plan is a documented and tested way of moving a service, its data, code and knowledge to another provider or to your own team without disrupting the business. It covers a list of what must be taken over, the format and timing of data return, a transition period during which the vendor keeps working, and the order of the handover. Financial entities must have such a plan for ICT services supporting critical or important functions (Article 28(8) DORA), but any company that depends on a single vendor benefits from one.
Why an exit plan when the relationship works
You write an exit plan while everything works, because that is when the vendor is willing to help. Once the relationship sours, the vendor fails or changes its terms, there is no time left to prepare, and every piece of information about the system becomes a bargaining chip.
An exit can be needed for many reasons: the vendor misses its service levels, is acquired by a competitor of the client, goes out of business, changes its prices or cannot meet new regulatory requirements. It can also be planned: a company builds its own team and wants to take over a system a partner has developed for years. In each case, whether the takeover takes weeks or months depends on what was prepared in advance.
What DORA requires
DORA has applied since January 17, 2025, and it explicitly requires exit plans in the financial sector:
- Article 28(8): for ICT services supporting critical or important functions, the financial entity has an exit strategy. It takes into account the risk of a failure on the provider's side, a deterioration in service quality, business disruption and termination of the contract. The entity must be able to exit the contract without disrupting its business, without limiting compliance with regulatory requirements and without harming the continuity and quality of services to clients. Exit plans must be comprehensive, documented, sufficiently tested and reviewed periodically. The entity identifies alternative solutions and transition plans that allow services and data to be moved securely to another provider or brought back in-house.
- Article 30(3)(f): the contract for such services includes an exit strategy with a mandatory, adequate transition period during which the provider keeps delivering the service while the entity moves it elsewhere.
- Article 28(7): sets out the situations in which the entity must be able to terminate the contract, for example a significant breach of laws or contract terms by the provider.
The full list of contract clauses is covered in the article IT vendor contracts under DORA, and how to record contracts in the article Register of contracts with ICT providers under DORA.
For cloud services there is also the Data Act, Regulation (EU) 2023/2854. Its Chapter VI places obligations on providers of data processing services that make it easier for customers to switch providers.
What an exit plan contains
| Element | What to record | Typical gap |
|---|---|---|
| Service scope | which systems, processes and tasks the vendor performs, including those not in the contract | tasks done “on the side”: nightly checks, manual corrections |
| Data | which data, in what format, by when it comes back, how to verify completeness | an export without metadata, history and attachments |
| Code and repositories | where the code is, who holds the rights, whether it can be built outside the vendor's environment | libraries and build scripts only on the vendor's server |
| Infrastructure | environment configuration, ideally as code, cloud accounts, certificates, domains | cloud accounts registered to the vendor |
| Access | a list of accounts, keys and permissions to take over or revoke | service accounts nobody remembers |
| Licenses and tools | licenses bought by the vendor, tools the system cannot run without | a license assigned to the vendor's company |
| Knowledge | who knows the system, what exists only in people's heads | no operational documentation |
| Transition period | how long the vendor keeps working, at what price, with what commitment | not in the contract |
| Alternatives | who takes over: another vendor, your own team, a technology change | an alternative invented only at exit time |
| Roles and decisions | who triggers the plan, who runs it, who signs off the end | no plan owner |
Infrastructure described as code can be rebuilt outside the vendor, which shortens an exit more than any documentation. We cover this in the article Infrastructure as code.
The handover: stages of an exit
An exit usually runs in four stages:
- Trigger. The decision, notice under the contract, setting up the receiving team, confirming the transition period.
- Preparation. Handing over documentation, code and access, a trial data export with a completeness check, preparing environments on the new team's side.
- Overlap. The new team first observes, then works alongside the vendor, and finally takes over alone, with the vendor available for questions. How to transfer knowledge during the overlap is covered in the article Knowledge transfer when a team member changes.
- Close. The final data export, revoking the vendor's access, confirmation that data has been deleted on its side, a closing report.
The criterion for ending the overlap should be practical: the new team has run a release on its own, handled a typical incident and closed a month, if the system has a monthly cycle. An example of taking over maintenance of a system with continuity of work is the maintenance team for a public administration line-of-business system.
How to test an exit plan
DORA requires exit plans to be sufficiently tested. A test does not mean changing vendors, only checking that the plan can be executed:
- a document review: is the list of systems, access and licenses current;
- a trial data export: does the data come back in the agreed format, and can it be loaded into another system;
- building the code outside the vendor: can your own team or another partner build and run the application from the repository;
- rebuilding an environment: does the infrastructure come up from configuration without manual steps by the vendor;
- a tabletop exercise: walking through the exit scenario with the people who would run it, asking “who does what in the first week”.
Record the test results together with the fixes. An exit plan is a close relative of the business continuity plan, so review both on the same cycle (see Business continuity: BCP and DRP). If you need a team to take over a system from your current vendor, reach us via contact.
Questions and answers
How does an exit strategy differ from an exit plan?
DORA uses both terms. An exit strategy is a company-level decision: what the alternatives to a given provider are and in which situations the company exits. An exit plan is the detailed execution: who takes over what, in what order and how fast. A strategy can cover a group of services, while a plan should exist for each service supporting a critical or important function.
Do you need an exit plan outside the financial sector?
The law requires it explicitly from financial entities covered by DORA, but it helps any company that depends on one vendor for an important system. Without a plan an exit takes longer, costs more and depends on the vendor's goodwill. In many cases a short version is enough: a list of data, code, access and licenses, plus a transition period written into the contract.
How long should the transition period be?
DORA does not give a number, it requires a period adequate to the service. The length depends on the system's complexity, the volume of data and whether the new team knows the technology. For a well-documented application weeks may be enough, for an older system without documentation it takes months. Derive the period from the handover plan rather than copying it from a template.
What if the vendor will not cooperate on the exit?
That is why the plan and the vendor's obligations must be written into the contract before any conflict: the transition period, the data format, documentation handover and payment for assistance. When the contract does not provide for this, negotiation is what remains. What helps most then is what you already hold: a copy of the code, documentation and your own knowledge of the system.