Skip to content
All projects

DORA compliance program: ICT provider register and resilience testing

Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
DORA has applied since January 2025, and the bank has scattered documentation: provider contracts in different formats, no classification of critical functions, and an incident procedure not adapted to the new reporting deadlines.
Approach
We work in four streams: a register of information on ICT contracts in the format required by the technical standards, incident classification and a reporting procedure, a resilience testing program proportionate to the bank's size, and an ICT risk management framework.
Goal
Closed compliance gaps: 100% of critical gaps before the supervisory deadline; Controls with automatically collected evidence: ≥ 60% of technical controls.

Client context

The Polish banking sector is highly digitized and at the same time operates under strict supervision by the KNF (Polish Financial Supervision Authority). Every change to a system used by customers must go through change control, testing and an acceptance process that can be shown to an auditor. The client is a cooperative bank affiliated with a banking association, using the association's IT services and several external providers, with a small IT and security team.

Challenge

DORA has applied since January 2025, and the bank has scattered documentation: provider contracts in different formats, no classification of critical functions, and an incident procedure not adapted to the new reporting deadlines. A small team cannot run day-to-day work and a compliance program at the same time.

Requirements and constraints

  • DORA, the Digital Operational Resilience Act (Regulation (EU) 2022/2554), requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) goes into the register of information on contractual arrangements. (source)
  • Recommendation D of the KNF (Polish Financial Supervision Authority) sets out the supervisor's expectations for managing information technology and the security of the ICT environment in banks: separation of environments, change control, access management and business continuity. Every change in the system must go through a test and acceptance path that can be shown to an auditor. (source)
  • The EBA Guidelines on outsourcing arrangements (EBA/GL/2019/02) require an assessment of whether a function is critical or important, provider due diligence, audit right clauses and an exit strategy. An external team must work in a way that lets the institution take over the knowledge and the work at any time. (source)
  • NIS2, Directive (EU) 2022/2555, and the amendment of the Polish National Cybersecurity System Act (KSC) require essential and important entities to implement cybersecurity risk management measures, supply chain security and incident reporting within short deadlines (an early warning within 24 hours). Management is personally accountable, so documenting decisions is part of the deliverable. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable handed over with documentation the client's team can take over.

Approach and architecture

We start with a gap analysis against the regulatory requirements and the standard, but the outcome is not just a report: it is a backlog of actions with owners, deadlines and evidence criteria. We write the documentation (policies, procedures, registers) so that it matches what the organization actually does, and we automate technical controls so that compliance evidence is produced continuously rather than assembled before each audit.

We work in four streams: a register of information on ICT contracts in the format required by the technical standards, incident classification and a reporting procedure, a resilience testing program proportionate to the bank's size, and an ICT risk management framework. We prepare the documents together with the banking association, so we do not duplicate what the central body already provides.

Key elements of the solution:

  • ICT contract register in a structured database with export to the reporting format
  • Incident classification decision tree aligned with the RTS criteria
  • Resilience testing calendar (vulnerability scans, restore tests, exercises)
  • Gap dashboard for the management board

Team and roles

RoleCountResponsibility
Project manager1plan, budget, risks, communication with the steering committee
Compliance specialist2requirements map, documentation, compliance evidence
Security architect1threat model, security requirements, design reviews
Test analyst (ISTQB)1designing and executing cases, reporting defects
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Gap analysis and risk assessment1–4gap report, risk register
2. Framework and documentation design5–8policies, procedures, registers
3. Implementation of technical controls9–15controls, evidence automation
4. Exercises and tests16–18incident exercises, resilience tests
5. Internal audit and maintenance plan19–20audit report, compliance calendar

Technology stack

Register database (PostgreSQL + forms), Power BI, vulnerability scanning tools, document templates in a version-controlled repository.

Risks and how we mitigate them

RiskHow we mitigate it
Diverging stakeholder expectationsstakeholder map, a shared definition of success, monthly steering committee
Regulations changed or clarified during the projectmonitoring of implementing acts, modular rule design, buffer in the schedule
Auditor or supervisor findings after deploymentcompliance function involved from the analysis phase, evidence collected along the way, review before acceptance
Knowledge held by single individualspair programming, documentation in the repository, backup plan for key roles

Measurable goals and KPIs

The values below are targets that we set with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
Closed compliance gaps100% of critical gaps before the supervisory deadlinecompliance backlog
Controls with automatically collected evidence≥ 60% of technical controlscontrol register
Time from detection to initial notification of a major incidentwithin the regulatory deadline (e.g. 4 h/24 h)exercises and incident register
Successful backup restore tests100% of quarterly testsrestore protocols

Lessons learned and good practices

The ICT provider register turns out to be the best tool for talking about risk concentration: for the first time you can see how many functions depend on a single provider. An incident exercise involving the management board is worth running early, because it exposes gaps in the procedure better than a document review. Documentation that describes reality survives an audit. Documentation written for the audit does not.

Why B2B.net

B2B.net S.A. has been operating since 2015 and has worked for more than 50 brands, mostly where audits are part of daily life: in banks, insurance and critical infrastructure. We are an accredited exam center, so testing methodology is not a claim for us but a working standard. We give a first proposal of engineers within 24 hours, and a team can start within 5 business days.

Next step

Facing a similar challenge? Write to office@b2bnetwork.pl or call: +48 577 317 312. You will get a first proposal of engineers or a plan for the first step within 24 hours.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk

B2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.

More projects: Banking