Data warehouse for regulatory and management reporting (FINREP/COREP)

Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
Preparing regulatory reports takes a large part of the month, and manual corrections in spreadsheets leave no trail.
Approach
We build a layered data warehouse with one definition per metric in a data catalog and lineage from the source to the report cell.
Goal
Time to prepare a regulatory or management report: down from days to hours; Share of records meeting quality rules: ≥ 98% in critical tables.

Client context

In banking, the cost of a production defect is measured not only in complaints but also in customer trust and supervisory findings. Since January 17, 2025, DORA has applied, moving the conversation about IT quality from the IT department to the board. The client is a universal bank with many data sources: the core, lending, treasury and card systems, with regulatory reports prepared in spreadsheets from exports of different systems.

Challenge

Preparing regulatory reports takes a large part of the month, and manual corrections in spreadsheets leave no trail. Different departments calculate the same metrics differently, which surfaces during reconciliation with finance and risk.

Requirements and constraints

  • Recommendation D of the KNF (Polish Financial Supervision Authority) sets out the supervisor's expectations for managing information technology and the security of the ICT environment in banks: separation of environments, change control, access management and business continuity. Every change in the system must go through a test and acceptance path that can be shown to an auditor. (source)
  • DORA, the Digital Operational Resilience Act (Regulation (EU) 2022/2554), requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) goes into the register of information on contractual arrangements. (source)
  • GDPR, Regulation (EU) 2016/679, requires data minimization, a legal basis for processing, processing agreements and, for high-risk processing, an impact assessment (DPIA). In practice it rules out copying production data into test environments without anonymization or pseudonymization. (source)
  • The KNF communication on cloud computing information processing describes the conditions under which supervised entities may use public or hybrid cloud services: risk estimation, information classification, data location, audit rights and an exit plan. Without a complete set of these documents, the migration will not pass the risk committee. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable handed over with documentation the client's team can take over.

Approach and architecture

We start with a handful of key metrics that are disputed today and design the data model backward from them. We run the migration from the existing warehouse in parallel: for a transition period both systems calculate the same figures, and automated reconciliation comparisons show discrepancies before the management board sees them.

We build a layered data warehouse with one definition per metric in a data catalog and lineage from the source to the report cell. Manual corrections do not disappear, but they go into an adjustments application with justification and approval. For three reporting periods the old and new processes run in parallel, with automated reconciliation.

Key elements of the solution:

  • Layers: staging → integrated model (Data Vault) → reporting data marts
  • Transformations in dbt with quality tests that block publication
  • Data catalog with lineage
  • Manual adjustments application with an audit trail

Team and roles

RoleCountResponsibility
Solution architect1target architecture, ADR decisions, technical reviews
Data engineer4pipelines, data model, data quality tests
BI analyst2dashboards, metric definitions, user training
Business analyst2requirements, processes, acceptance criteria
Test analyst (ISTQB)1designing and executing cases, reporting defects
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Inventory of sources and metrics1–5metric glossary, source map
2. Architecture and data model6–12layered model, standards
3. Building pipelines and quality tests13–25pipelines, tests, catalog
4. Reconciliation and parallel run26–32compliance reports
5. Rollout and training33–36dashboards, training, handover

Technology stack

Oracle Exadata or Snowflake (decision after the KNF_CHM assessment), dbt, Airflow, Great Expectations, OpenMetadata, Power BI.

Risks and how we mitigate them

RiskHow we mitigate it
Data migration errorsdata profiling, trial migrations with reconciliation, quality criteria before cutover
Diverging stakeholder expectationsstakeholder map, a shared definition of success, monthly steering committee
Undocumented behavior of the old systemcharacterization tests (golden master) before the change, old versus new result comparisons
Auditor or supervisor findings after deploymentcompliance function involved from the analysis phase, evidence collected along the way, review before acceptance

Measurable goals and KPIs

The values below are targets that we set with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
Time to prepare a regulatory or management reportdown from days to hoursbefore/after measurement
Share of records meeting quality rules≥ 98% in critical tablesdata quality tests
Old versus new system reconciliation discrepancies0 unexplained discrepancies before cutoverreconciliation report
Data freshness in reports≤ D+1 (or ≤ 15 min for operational data)pipeline metadata

Lessons learned and good practices

A dispute over a metric definition has to be settled before modeling, not after the first report. Data lineage cuts conversations with the audit from weeks to a single meeting. Data quality tests must block publication, otherwise nobody reads them.

Why B2B.net

We combine two models: we provide individual engineers and whole teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the outcome, we work at a fixed price for a defined scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies and experience with ISO 27001, DORA and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.

Next step

If you recognize these problems in your own organization, let's start with a short diagnosis: one workshop with your team and a written recommendation. Write to us: office@b2bnetwork.pl.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk