The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.
In brief
- Problem
- The project covers authorizations, settlement with card schemes, chargebacks, loyalty programs and a digital wallet.
- Approach
- We build a catalog of card processes with a risk assessment, and end-to-end scenarios covering the whole card lifecycle: issuance, activation, authorizations (including offline), settlement, chargeback, blocking, renewal.
- Goal
- Defect detection effectiveness (DDE): ≥ 90%; Critical defects found after deployment: 0 critical defects in the first 30 days.
Client context
The Polish banking sector is highly digitized and at the same time operates under strict supervision by the KNF (Polish Financial Supervision Authority). Every change to a system used by customers must go through change control, testing and an acceptance process that can be shown to an auditor. The client is a retail bank replacing its debit and credit card management system with a third-party solution, migrating several hundred thousand cards.
Challenge
The project covers authorizations, settlement with card schemes, chargebacks, loyalty programs and a digital wallet. The vendor tests its own product, but nobody tests the bank's processes end to end, including edge cases from settlement.
Requirements and constraints
- PCI DSS v4.0 applies to anyone who processes payment card data. Version 4.0 tightens requirements for multi-factor authentication, scripts on payment pages and segmentation penetration tests. (source)
- Recommendation D of the KNF (Polish Financial Supervision Authority) sets out the supervisor's expectations for managing information technology and the security of the ICT environment in banks: separation of environments, change control, access management and business continuity. Every change in the system must go through a test and acceptance path that can be shown to an auditor. (source)
- PSD2 and the RTS on strong customer authentication (SCA) require strong customer authentication, secure interfaces for third-party providers (TPPs) and transaction monitoring for fraud. Every change to a payment path requires tests of SCA exemptions and of API availability compliance. (source)
- DORA, the Digital Operational Resilience Act (Regulation (EU) 2022/2554), requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) goes into the register of information on contractual arrangements. (source)
- Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable handed over with documentation the client's team can take over.
Approach and architecture
We follow a test process based on ISTQB: test basis analysis, test case design using black-box techniques (equivalence classes, boundary values, decision tables, state transitions), and then execution with full traceability to requirements. Test priority comes from product risk analysis, not from the order in the specification: we first check what hurts the customer and the supervisor when it stops working.
We build a catalog of card processes with a risk assessment, and end-to-end scenarios covering the whole card lifecycle: issuance, activation, authorizations (including offline), settlement, chargeback, blocking, renewal. We design edge cases (currencies, partial refunds, late transactions) using decision table and state transition techniques.
Key elements of the solution:
- Process catalog with traceability to requirements and scenarios
- Simulators for authorizations and settlement files
- Migration tests on card samples with reconciliation
- Weekly quality report for the steering committee
Team and roles
| Role | Count | Responsibility |
|---|---|---|
| Test manager (ISTQB Advanced) | 1 | test strategy, entry and exit criteria, quality reporting |
| Test analyst (ISTQB) | 5 | designing and executing cases, reporting defects |
| Test automation engineer | 1 | framework, scripts, CI integration |
| Business analyst | 1 | requirements, processes, acceptance criteria |
| Product owner and domain experts (client side) | as needed | priorities, business decisions, acceptance |
Phased schedule
| Phase | Weeks | Deliverable |
|---|---|---|
| 1. Analysis and test strategy | 1–4 | test strategy, risk matrix, environment plan |
| 2. Test case design | 5–10 | case repository with traceability |
| 3. System and integration testing | 11–20 | daily reports, defect register |
| 4. User acceptance testing (UAT) with the business | 21–26 | UAT protocols, exit criteria |
| 5. Closure report and handover | 27–28 | quality report, recommendations |
Technology stack
Jira Xray, card scheme simulators, SQL, Postman, Excel/Power BI for reconciliation.
Risks and how we mitigate them
| Risk | How we mitigate it |
|---|---|
| Dependence on an external provider and its deadlines | early agreement on API contracts, a stub environment, weekly dependency review |
| Test environments unavailable or unstable | environment booking schedule, virtualization of external services (mocks), daily environment smoke test |
| Data migration errors | data profiling, trial migrations with reconciliation, quality criteria before cutover |
| Cutover risk | at least two dress rehearsals, a rollback plan with decision criteria, a maintenance window during low traffic |
Measurable goals and KPIs
The values below are targets that we set with the client after a baseline measurement in the first phase.
| KPI | Target | How it is measured |
|---|---|---|
| Defect detection effectiveness (DDE) | ≥ 90% | defects found in testing / all defects within 90 days |
| Critical defects found after deployment | 0 critical defects in the first 30 days | production incident register |
| Old versus new system reconciliation discrepancies | 0 unexplained discrepancies before cutover | reconciliation report |
Lessons learned and good practices
Most defects hide in settlement files and chargebacks, which is where the vendor tests the least. Migration tests on samples need to start early, because they expose problems with source data quality. Exit criteria agreed before testing starts save weeks of arguments at the end of the project.
Why B2B.net
B2B.net S.A. has been operating since 2015 and has worked for more than 50 brands, mostly where audits are part of daily life: in banks, insurance and critical infrastructure. We are an accredited exam center, so testing methodology is not a claim for us but a working standard. We give a first proposal of engineers within 24 hours, and a team can start within 5 business days.
Next step
Let's talk about your project. Within 24 hours we will get back to you with a quote or a proposal of engineers; a team can start within 5 business days. Contact: office@b2bnetwork.pl.
What would this look like for you?
Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.