The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.
In brief
- Problem
- Teams wait for environments, and the ones that exist differ from production.
- Approach
- We start with a risk assessment and information classification: only environments with synthetic data land in the cloud.
- Goal
- Lead time from change approval to production (DORA metrics): < 1 day; Infrastructure cost per transaction or user: a decrease against the baseline, target set after phase 1.
Client context
In banking, the cost of a production defect is measured not only in complaints but also in customer trust and supervisory findings. Since January 17, 2025, DORA has applied, moving the conversation about IT quality from the IT department to the board. The client is a universal bank with its own data center, where preparing a new test environment takes weeks and blocks the product teams.
Challenge
Teams wait for environments, and the ones that exist differ from production. The bank wants to move non-production environments to the cloud, but it must meet the requirements of the KNF cloud communication and DORA.
Requirements and constraints
- The KNF communication on cloud computing information processing describes the conditions under which supervised entities may use public or hybrid cloud services: risk estimation, information classification, data location, audit rights and an exit plan. Without a complete set of these documents, the migration will not pass the risk committee. (source)
- DORA, the Digital Operational Resilience Act (Regulation (EU) 2022/2554), requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) goes into the register of information on contractual arrangements. (source)
- GDPR, Regulation (EU) 2016/679, requires data minimization, a legal basis for processing, processing agreements and, for high-risk processing, an impact assessment (DPIA). In practice it rules out copying production data into test environments without anonymization or pseudonymization. (source)
- The EBA Guidelines on outsourcing arrangements (EBA/GL/2019/02) require an assessment of whether a function is critical or important, provider due diligence, audit right clauses and an exit strategy. An external team must work in a way that lets the institution take over the knowledge and the work at any time. (source)
- Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable handed over with documentation the client's team can take over.
Approach and architecture
We build an internal developer platform: a product team gets ready-made service templates, a pipeline and observability instead of configuring everything from scratch. Deployments follow GitOps, with the ability to roll back instantly, and cloud costs are tagged to teams and shown every week (FinOps).
We start with a risk assessment and information classification. Only environments with synthetic data land in the cloud. We build a landing zone with policies as code, and test environments become ephemeral: created from a template for a branch and deleted after the merge. The cloud exit plan is tested, not just described.
Key elements of the solution:
- Landing zone with separate subscriptions for teams
- Environment templates (Terraform + Helm) launched from the pipeline
- Synthetic data generator
- Central logging and Azure Policy/OPA policies
Team and roles
| Role | Count | Responsibility |
|---|---|---|
| Cloud architect | 1 | landing zone, networking, cloud security, costs |
| DevOps engineer | 3 | CI/CD pipeline, infrastructure as code |
| SRE engineer | 1 | observability, SLOs, incident procedures |
| Security architect | 1 | threat model, security requirements, design reviews |
| Product owner and domain experts (client side) | as needed | priorities, business decisions, acceptance |
Phased schedule
| Phase | Weeks | Deliverable |
|---|---|---|
| 1. Readiness assessment and migration plan | 1–5 | inventory, 6R paths, business case |
| 2. Landing zone and security | 6–12 | accounts/subscriptions, networking, IAM, policies |
| 3. Migration in waves | 13–26 | migrated applications, runbooks |
| 4. Optimization and FinOps | 27–31 | right-sizing, cost report |
| 5. Operations handover | 32–36 | documentation, on-call rotations, training |
Technology stack
Azure, AKS, Terraform, Helm, Argo CD, Azure Policy, OPA Gatekeeper, Key Vault.
Risks and how we mitigate them
| Risk | How we mitigate it |
|---|---|
| Uncontrolled growth of cloud costs | budgets and alerts, tagging, weekly FinOps review, reservations once the workload stabilizes |
| No test data free of personal data | synthetic data generator and masking that preserves referential integrity; no copying production into test |
| Auditor or supervisor findings after deployment | compliance function involved from the analysis phase, evidence collected along the way, review before acceptance |
| Knowledge held by single individuals | pair programming, documentation in the repository, backup plan for key roles |
Measurable goals and KPIs
The values below are targets that we set with the client after a baseline measurement in the first phase.
| KPI | Target | How it is measured |
|---|---|---|
| Lead time from change approval to production (DORA metrics) | < 1 day | repository and pipeline data |
| Infrastructure cost per transaction or user | a decrease against the baseline, target set after phase 1 | FinOps report |
| Deployment frequency | on demand, at least weekly | CD pipeline |
Lessons learned and good practices
Ephemeral environments change the conversation about costs: you pay for test time, not for a permanent fleet of machines. A cloud exit plan only becomes credible once it has been rehearsed. Cloud costs need to be shown to teams from the first week, not after the first invoice.
Why B2B.net
We combine two models: we provide individual engineers and whole teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the outcome, we work at a fixed price for a defined scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies and experience with ISO 27001, DORA and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.
Next step
If you recognize these problems in your own organization, let's start with a short diagnosis: one workshop with your team and a written recommendation. Write to us: office@b2bnetwork.pl.
What would this look like for you?
Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.
Let's talkB2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.