In brief
The Product Owner should sit on the client side, because they are accountable for the product's value and decide the order of work, and those decisions cannot be handed to an outside company without losing control of the product. The Scrum Master can come from the vendor, especially when most of the team are the vendor's engineers. The vendor can also provide an analyst who helps the Product Owner prepare the backlog, but the decisions and the accountability stay with the client.
What the Scrum Guide says about the roles
The 2020 Scrum Guide describes a Scrum Team as one Scrum Master, one Product Owner and Developers, typically 10 or fewer people in total. There are no sub-teams or hierarchies within the team. For working with a vendor, three points from the guide matter most:
- The Product Owner is one person, not a committee. They are accountable for maximizing the value of the product resulting from the team's work. They can delegate some of the work, such as writing backlog items, but they remain accountable.
- The Scrum Master is accountable for establishing Scrum as defined in the guide and for the team's effectiveness. They remove impediments, help the team and the organization understand Scrum, and make sure Scrum events take place and are productive.
- Several teams working on one product share the same Product Goal, the same Product Backlog and one Product Owner.
The guide says nothing about contracts or which company employs whom. You have to answer those questions yourself, but the guide's principles set the boundaries.
Product Owner: why on the client side
The Product Owner decides what the team does in the next sprint and what it does not do at all. These are business decisions: which feature brings revenue, which regulatory requirement has a deadline, what to drop. A person on the vendor's side does not know the client's goals as well and has a different interest. Even an honest vendor that sets priorities is in practice deciding what the client pays for.
Typical setups and their consequences:
| Setup | How it works | Risk |
|---|---|---|
| Client's Product Owner, full time | decisions are fast, the backlog is current | none, if the person has a business mandate |
| Client's Product Owner part time, vendor analyst prepares the backlog | the analyst writes items, the Product Owner approves the order | the analyst starts deciding for the Product Owner when they lack time |
| Product Owner on the vendor's side | the vendor decides the scope | the client loses control of the product and the cost |
| A committee instead of a Product Owner | decisions in meetings of several people | the team waits for decisions, priorities keep shifting |
The most common problem is a client Product Owner who holds the role on top of another job. The team then works on whatever has been written up, not on what matters most. If the client cannot provide a full-time Product Owner, it is better to give backlog preparation to the vendor's analyst and leave decisions and the Sprint Review to the Product Owner than to pretend the Product Owner has time for everything.
Scrum Master: when on the vendor's side
The Scrum Master does not decide about the product, only about how the team works. So they can come from the company that employs most of the team. When all the Developers are the vendor's engineers, a vendor Scrum Master knows them, knows how to arrange cover and owns the way of working, which fits a model where the vendor takes responsibility for the team's composition and methods. The differences between the models are covered in the article Team leasing vs project outsourcing.
When the team is mixed and the client has its own agile practice with other Scrum Masters, the Scrum Master is better placed on the client side. The team then works to the same rules as the rest of the organization.
Be careful with combining roles. A vendor Scrum Master who is also the account manager has a conflict of interest: as Scrum Master they should surface impediments, including those on the vendor's side, while as account manager they protect the contract.
The contract and Scrum
Scrum assumes the scope changes and the Product Owner sets the order every sprint. A fixed-scope, fixed-price contract contradicts that: every change in the backlog becomes a contract change. Scrum with a vendor works best when billing is for the team's time or a fixed monthly amount, as we describe in the article Time and materials or fixed price.
The contract should record:
- Who holds the Scrum roles on each side and what mandate they have, for example whether the Product Owner can change the Sprint Goal alone.
- The Definition of Done, shared by all teams working on the product. Under the Scrum Guide an item that does not meet it returns to the backlog and is not presented at the Sprint Review.
- What billing is based on: time worked with a report by task, not story points that the team estimates itself.
- How acceptance works, if the contract requires it: for example quarterly, based on the increments shown at Sprint Reviews. Details in the article Acceptance in an IT project.
Scrum events across company boundaries
Scrum events work the same way, but they are easier to break when people from two companies take part:
- Sprint Planning needs the Product Owner. Without them the team plans based on its own guesses.
- The Daily Scrum is for the Developers. When a client-side manager starts using it to hold the vendor's people to account, it turns into a status report and people stop talking about problems.
- The Sprint Review is the place for the client's stakeholders. That is where the client sees working software, not a timesheet.
- The Retrospective should be joint. Separate retrospectives for client and vendor people hide problems that sit at the boundary between the companies, such as waiting for access or for decisions.
When people work in several cities or countries, shared hours and tools come into play, as we describe in the article A team across several cities. An example of external analysts and testers working to the client's sprint cadence is the team of analysts and testers for a product change program. The roles we fill in such teams are in the section What we do.
Questions and answers
Can the Product Owner be a vendor employee?
The Scrum Guide does not forbid it, but in practice it is risky. The Product Owner decides the product's value and the order of work, which means what the client spends money on. If a vendor's person does that, the client loses control of the product. It is safer for the vendor to provide an analyst who prepares the backlog and leave the decisions to the client's Product Owner.
Who should be Scrum Master in a mixed team?
It depends on who employs most of the team and whose ways of working apply. When the team is mostly the vendor's engineers, a vendor Scrum Master knows them and owns their way of working. When the client has its own agile practice, the Scrum Master is better taken from the client's organization. What matters is that they do not combine the role with managing the contract.
Can several vendors work on one product in Scrum?
Yes. Under the Scrum Guide teams working on one product share a Product Goal, one Product Backlog and one Product Owner. Each vendor can have its own team and its own Scrum Master, but the Definition of Done and the backlog must be shared. Without that, integrating the teams' work turns into a separate project at the end.
Can you run Scrum under a fixed-price contract?
You can, with limits. A fixed scope and price clash with the Product Owner's right to reorder work every sprint. Compromises include a contract with a budget and a goal instead of a detailed specification, swapping backlog items of similar size without an amendment, or fixed price for short phases with a scope review after each one.