Time and materials or fixed price: how to choose a billing model

B2Bnetwork team · · 6 min

Engineering teams

In brief

Choose fixed price when the scope can be described and verified before work starts and few changes are expected. Choose time and materials when requirements will change or you are still discovering them. Under fixed price the contractor takes the cost risk and builds it into the price. Under time and materials you pay for the actual time worked, so the risk sits with you, but you can change course freely. With an uncertain scope, a short fixed-price analysis followed by a decision on the model is a good compromise.

What the two models are

Time and materials (T&M) is billing for the time actually worked and costs actually incurred at agreed rates, usually per hour, day or month for each role. The scope can change along the way, and each period you receive a time report and decide what the team works on next.

Fixed price (FP) is a set price for an agreed scope, usually with a schedule, milestones and acceptance criteria. The contractor commits to delivering the outcome for that price, regardless of how much work it actually takes.

In Polish law, fixed price corresponds to the lump-sum fee in Article 632 of the Civil Code: the contractor cannot demand a higher lump sum even if the extent of the work could not be foreseen when the contract was signed. The exception is an unforeseeable change in circumstances under which performance would expose the contractor to a grossly excessive loss: a court may then raise the lump sum or dissolve the contract. The Code also provides for a cost-estimate fee (Article 629), calculated from a schedule of planned work and costs.

Who carries which risk

MatterTime and materialsFixed price
Risk that the work takes longeryouthe contractor
Scope change midwayno formalities, it costs timechange procedure, pricing, contract amendment
Preparation before startshort, a backlog is enoughlong: specification, acceptance criteria
Pricedepends on the actual workknown upfront, with a risk buffer
Direction of the workyou, or sharedthe contractor
Transparencytime and progress reportsprogress by milestones and acceptance
Typical disputewhether the work was efficientwhether a change is within scope

A contractor that takes on risk under fixed price prices it in. With a well-described scope the buffer is small. With a vague scope the buffer grows, or the contractor defends itself with a narrow reading of the specification and every ambiguity becomes a separately priced change. That is why fixed price on an unclear scope often costs more than time and materials on the same scope.

How the billing model relates to responsibility for the result is covered in the article Team leasing vs project outsourcing.

When each model fits

Fixed price works when:

  • the outcome can be described as a list of requirements and verified with acceptance tests;
  • the technology and the systems to integrate with are known;
  • the work has a clear end, for example a performance test before a sales peak, a data migration from one database to another, or integrating an online store with a warehouse system;
  • you need a firm figure in the budget or you are buying through a tender.

An example is preparing an online store for Black Friday: the goal, the deadline and the way of measuring are known before the start.

Time and materials works when:

  • requirements are discovered along the way, for example with a new product or modernizing a system without documentation;
  • the work is ongoing: product development, maintenance, regression on every release;
  • you work in Scrum and want to change priorities every sprint;
  • you have a person who directs the team's work every day.

The agile approach says this outright: the Agile Manifesto values customer collaboration over contract negotiation and responding to change over following a plan. Fixed price on a product developed in sprints usually ends in a scope dispute every sprint.

Hybrid models

Between the pure models there are several proven variants:

  1. Fixed-price analysis, delivery later. A short phase ends with a description of scope, risks and an estimate. Then you know whether to order delivery as fixed price or as time and materials.
  2. Fixed price per phase. A large project is split into phases, each with its own price. The next phase is priced once the previous one is accepted, so the risk of a bad estimate covers only one piece.
  3. Time and materials with a cap. You pay for actual time, but the contract sets a maximum amount per period or per goal. Going over requires your approval.
  4. A stable team for a fixed monthly amount. You know the monthly cost, and the scope is set every sprint. This is time and materials with a predictable budget, typical for development and maintenance teams.

Whatever the variant, compare offers on the same scope and in the same unit. How to convert hourly, daily and monthly rates is covered in the article IT rates, and current ranges for roles are in our rate report.

How to keep a time and materials budget on track

Time and materials does not mean a lack of control. Agree before you start on:

  • a budget per period and a warning threshold, for example a notice when spending passes an agreed percentage;
  • a time report by task, not only by person, so you can see what a specific feature cost;
  • a progress review every sprint with a demo of working software, not just a list of hours;
  • a definition of done, so that “done” means the same thing to both sides;
  • a forecast to completion, updated monthly: how much work is left in the backlog and what it will cost.

Under fixed price control looks different: you guard the scope and the acceptance steps. Record every change through the change procedure, because a change agreed verbally comes back at settlement time. How to describe acceptance of a phase is shown in the article Acceptance in an IT project.

Questions and answers

Does fixed price always give cost certainty?

Only with a stable scope. Every change in requirements, every new integration or requirement that surfaces midway goes through the change procedure and raises the price. If the scope was described loosely, there will be many such changes, and the final cost may exceed what time and materials would have cost. Cost certainty comes from a well-described scope, not from the billing model itself.

Is the contractor responsible for the deadline under time and materials?

Usually not, because it does not control scope or priorities. It answers for diligent work, people's availability and accurate reporting. You can protect the deadline in other ways: a budget cap, a progress review every sprint and a forecast to completion. If you need a commitment to a date, describe the scope and order it as fixed price.

How do you bill a project where part of the scope is known and part is not?

Split it. Order the known part, for example a data migration or an integration with a known API, as fixed price with acceptance criteria. Run the uncertain part, for example new user features, as time and materials with a cap. You can also start with a fixed-price analysis that turns the uncertain part into a known one.

Which model do banks and insurers choose?

Both, depending on the work. Regulatory programs with a hard deadline and a clear scope often go as fixed price per phase. Digital channel development, maintenance and regression testing usually go as time and materials or a stable team. Either way, the contract with an ICT provider must meet the DORA requirements described in the article IT vendor contracts under DORA.

What it looks like in a project