Acceptance testing of a CRM implementation at a service company

Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
The CRM vendor delivers a configuration, but the company lacks the expertise to check whether the system supports its processes: tickets, service contracts, SLAs, spare parts.
Approach
We prepare acceptance test scenarios based on real tickets from recent months and run UAT with dispatchers and technicians.
Goal
Defect detection effectiveness (DDE): ≥ 90%; critical defects found after deployment: 0 critical defects in the first 30 days.

Client context

Service companies, from restaurant chains to consulting firms, grow faster than their IT back office. Their processes rely on e-mails and spreadsheets, which stop being enough with the next branch. A service company maintaining refrigeration equipment in shops, deploying a new CRM and a mobile app for technicians.

Challenge

The CRM vendor delivers a configuration, but the company lacks the expertise to check whether the system supports its processes: tickets, service contracts, SLAs, spare parts.

Requirements and constraints

  • GDPR, that is Regulation (EU) 2016/679, requires data minimization, a legal basis for processing, data processing agreements and, for high-risk processing, a data protection impact assessment (DPIA). In practice it rules out copying production data into test environments without anonymization or pseudonymization. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable supplied with documentation that the client's team can take over.

Approach and architecture

We work according to an ISTQB-based test process: test basis analysis, test case design with black-box techniques (equivalence partitioning, boundary values, decision tables, state transitions), and then execution with full traceability to requirements. Test priority comes from product risk analysis, not from the order in the specification: first we check what hurts the client and the supervisors when it stops working.

We prepare acceptance test scenarios based on real tickets from recent months and run UAT with dispatchers and technicians. Defects and gaps are categorized and passed to the vendor with a priority.

Key elements of the solution:

  • Scenarios based on real tickets
  • Testing the technician's app in the field (weak signal)
  • SLA calculation tests
  • Categorization of gaps and defects for the vendor

Team and roles

RoleCountResponsibility
Test manager (ISTQB Advanced)1test strategy, entry and exit criteria, quality reporting
Test analyst (ISTQB)2designing and executing test cases, reporting defects
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Analysis and test strategy1–2test strategy, risk matrix, environment plan
2. Test case design3–4test case repository with traceability
3. System and integration testing5–8daily reports, defect register
4. Acceptance testing (UAT) with the business9–10UAT protocols, exit criteria
5. Closure report and handover11–11quality report, recommendations

Technology stack

Jira, the client's CRM, a mobile app, Excel.

Risks and how we mitigate them

RiskHow we mitigate it
Dependence on an external vendor and its deadlinesearly agreement on API contracts, a stub environment, a weekly dependency review
Scope creep during the projecta backlog with MoSCoW priorities, every change goes through the committee with an estimate of its impact on the deadline
Diverging stakeholder expectationsa stakeholder map, a shared definition of success, a monthly steering committee

Measurable goals and KPIs

The values below are targets that we set with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
Defect detection effectiveness (DDE)≥ 90%defects found in testing / all defects within 90 days
Critical defects found after deployment0 critical defects in the first 30 daysproduction incident register

Lessons learned and good practices

Scenarios based on real tickets uncover gaps that are not in the specification. Testing the app in the field, with a weak signal, is essential. Exit criteria agreed before testing starts save weeks of disputes at the end of the project.

Why B2B.net

B2B.net S.A. has operated since 2015 and has worked for over 50 brands, mainly where audit is an everyday reality: in banks, insurance and critical infrastructure. We are an accredited exam center, so a testing methodology is not a claim for us but a working standard. We give a first proposal of specialists within 24 hours, and a team can start within 5 business days.

Acceptance criteria

Each phase ends with a formal acceptance against criteria agreed at the start. In this implementation, acceptance covers: a test strategy, risk matrix and environment plan; a test case repository with traceability; daily reports and a defect register; UAT protocols and exit criteria; a quality report and recommendations. Final acceptance requires a KPI measurement report against the baseline, complete documentation handed over to the client's team, and a list of recommendations for the next stage, with a cost and risk assessment for each.

Next step

Let's talk about your project. Within 24 hours we will come back with a quote or a proposal of engineers; a team can start within 5 business days. Contact: office@b2bnetwork.pl.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk

B2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.

More projects: Services