Independent acceptance testing of a provincial office's e-services system

Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
The contracting authority has no testing team of its own and accepts the system based on the contractor's reports.
Approach
We act as an independent testing team on the contracting authority's side: a traceability matrix from the requirements in the terms of reference (OPZ) to tests, acceptance testing of every stage, accessibility and security testing, and an acceptance recommendation for the committee.
Goal
Defect detection effectiveness (DDE): ≥ 90%; WCAG 2.1 AA compliance: 0 critical errors in the audit.

Client context

Public administration is digitizing services for citizens and businesses, and the requirements for interoperability, accessibility, and security are written into law here, not just into good practice. The client is an office running a project to digitize services for citizens and businesses, with a contractor selected in a tender and formal acceptance of each stage.

Challenge

The contracting authority has no testing team of its own and accepts the system based on the contractor's reports. There is no independent assessment of whether the system meets the requirements in the terms of reference (OPZ).

Requirements and constraints

  • The Polish Public Procurement Law affects how work is settled (often a fixed price for a defined scope), the requirements for copyright and handover of source code, and formal acceptance of stages. The schedule must account for the contracting authority's acceptance procedures. (source)
  • The National Interoperability Framework (KRI) sets minimum requirements for the IT systems of public bodies: interoperability, security, accessibility, and internal audit. The project must leave behind documentation that lets the contracting authority pass an inspection. (source)
  • WCAG 2.1/2.2 (W3C) and the Polish Digital Accessibility Act: level AA is mandatory for public bodies, and the accessibility statement must be kept up to date. Accessibility testing must combine automated tools with expert review and screen reader testing. (source)
  • GDPR, i.e. Regulation (EU) 2016/679, requires data minimization, a legal basis for processing, processing agreements, and, for high-risk processing, a data protection impact assessment (DPIA). In practice it rules out copying production data into test environments without anonymization or pseudonymization. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, and every deliverable shipped with documentation the client's team can take over.

Approach and architecture

We start with a risk-based test strategy: together with process owners we assess the likelihood and impact of failure in each area, and the result determines how deep the testing goes. Test cases are designed by ISTQB-certified analysts, and every defect gets a root cause classification, so after a few sprints it is clear where most errors originate and what to improve in the development process.

We act as an independent testing team on the contracting authority's side: a traceability matrix from the requirements in the terms of reference (OPZ) to tests, acceptance testing of every stage, accessibility and security testing, and an acceptance recommendation for the committee.

Key elements of the solution:

  • Traceability matrix from the OPZ to tests
  • Acceptance testing of stages
  • WCAG 2.1 AA accessibility audit
  • Acceptance recommendation for the committee

Team and roles

RoleCountResponsibility
Test manager (ISTQB Advanced)1test strategy, entry and exit criteria, quality reporting
Test analyst (ISTQB)3designing and executing test cases, reporting defects
Pentester (OSCP/OSWE)1manual testing, exploitation, remediation recommendations
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Analysis and test strategy1–4test strategy, risk matrix, environment plan
2. Test case design5–9test case repository with traceability
3. System and integration testing10–17daily reports, defect register
4. User acceptance testing (UAT) with the business18–22UAT protocols, exit criteria
5. Closure report and handover23–24quality report, recommendations

Technology stack

Jira Xray or TestRail, axe-core, NVDA, Burp Suite, SQL.

Risks and how we mitigate them

RiskHow we mitigate it
Dependence on an external vendor and its deadlinesearly agreement on API contracts, a stub environment, a weekly dependency review
Diverging stakeholder expectationsstakeholder map, a shared definition of success, a monthly steering committee
Scope creep during the projecta backlog prioritized with MoSCoW, every change goes through the committee with a schedule impact estimate
Auditor or regulator comments after go-livecompliance involved from the analysis phase, evidence collected along the way, a review before acceptance

Measurable goals and KPIs

The values below are targets that we set with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
Defect detection effectiveness (DDE)≥ 90%defects found in testing / all defects within 90 days
WCAG 2.1 AA compliance0 critical errors in the auditexpert and automated audit
Critical defects found after go-live0 critical defects in the first 30 daysproduction incident log

Lessons learned and good practices

Independent testing on the contracting authority's side turns acceptance from a formality into real verification. The OPZ traceability matrix is the best tool in disputes with the contractor. Traceability from requirements to tests is cheap when built from day one and very expensive when reconstructed before an audit.

Why B2B.net

We combine two models: we provide individual specialists and entire teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the outcome, we work at a fixed price for a defined scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies, and experience with ISO 27001, DORA, and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.

Next step

Want to see what such an implementation would look like in your organization? Book a 30-minute call. We will prepare a plan for the first six weeks and a team composition tailored to your system.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk

B2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.

More projects: Public sector