The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.
In brief
- Problem
- Services are scattered across several websites and line-of-business systems.
- Approach
- One portal with sign-in through the national node, integrations with line-of-business systems, and payments.
- Goal
- WCAG 2.1 AA compliance: 0 critical errors in the audit; Active users of the solution: ≥ 80% of the target group after 3 months.
Client context
Public bodies run IT projects under public procurement rules, with formal acceptance of stages and digital accessibility obligations. Systems must run for years and be maintainable by successive contractors. The client is a city office that wants to offer residents official matters online: requests, local payments, appointment booking, and case information.
Challenge
Services are scattered across several websites and line-of-business systems. Residents call to ask about the status of their cases, and queues at the office are long.
Requirements and constraints
- The Polish Public Procurement Law affects how work is settled (often a fixed price for a defined scope), the requirements for copyright and handover of source code, and formal acceptance of stages. The schedule must account for the contracting authority's acceptance procedures. (source)
- The National Interoperability Framework (KRI) sets minimum requirements for the IT systems of public bodies: interoperability, security, accessibility, and internal audit. The project must leave behind documentation that lets the contracting authority pass an inspection. (source)
- WCAG 2.1/2.2 (W3C) and the Polish Digital Accessibility Act: level AA is mandatory for public bodies, and the accessibility statement must be kept up to date. Accessibility testing must combine automated tools with expert review and screen reader testing. (source)
- GDPR, i.e. Regulation (EU) 2016/679, requires data minimization, a legal basis for processing, processing agreements, and, for high-risk processing, a data protection impact assessment (DPIA). In practice it rules out copying production data into test environments without anonymization or pseudonymization. (source)
- eIDAS 2.0, i.e. Regulation (EU) 2024/1183, establishes the European Digital Identity Wallet and a framework for electronic signatures and seals. Remote identification processes should be designed so that the EUDI wallet can be adopted as another authentication method. (source)
- Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, and every deliverable shipped with documentation the client's team can take over.
Approach and architecture
We build the product in short iterations with a working increment every sprint. We design the architecture so that business changes do not require rewriting the core: clear module boundaries, API contracts designed before implementation, contract tests, and feature flags that let us deploy code before a feature is switched on. Quality is built into the definition of done: code review, tests, static analysis, and accessibility.
One portal with sign-in through the national node, integrations with line-of-business systems, and payments. We design with residents (usability testing), build in accessibility from the first sprint, and hand over the source code and documentation to the contracting authority.
Key elements of the solution:
- Sign-in through the national node (Trusted Profile, e-ID card)
- Integrations with the office's line-of-business systems
- Local payments
- Handover of source code and documentation
Team and roles
| Role | Count | Responsibility |
|---|---|---|
| Project manager | 1 | plan, budget, risks, communication with the steering committee |
| Business analyst | 1 | requirements, processes, acceptance criteria |
| UX/UI designer | 1 | research, prototypes, usability and accessibility testing |
| Frontend developer (React/Angular) | 2 | interface, accessibility, component tests |
| Backend developer (Java/Kotlin) | 3 | domain services, API, unit tests |
| Test analyst (ISTQB) | 2 | designing and executing test cases, reporting defects |
| Product owner and domain experts (client side) | as needed | priorities, business decisions, acceptance |
Phased schedule
| Phase | Weeks | Deliverable |
|---|---|---|
| 1. Discovery and prototype | 1–5 | journey map, backlog, prototype |
| 2. Architecture and foundations | 6–10 | ADRs, skeleton, CI/CD |
| 3. Iterative development | 11–26 | an increment every sprint, demos |
| 4. Stabilization and acceptance testing | 27–31 | UAT, security and accessibility testing |
| 5. Deployment and post-launch support | 32–36 | go-live, hypercare, handover |
Technology stack
Angular, Java, Spring Boot, PostgreSQL, Keycloak, integration with the national node, Kubernetes.
Risks and how we mitigate them
| Risk | How we mitigate it |
|---|---|
| Scope creep during the project | a backlog prioritized with MoSCoW, every change goes through the committee with a schedule impact estimate |
| Non-compliance with accessibility requirements | screen reader testing in every sprint, components accessible by design, an expert audit before release |
| Dependence on an external vendor and its deadlines | early agreement on API contracts, a stub environment, a weekly dependency review |
| Diverging stakeholder expectations | stakeholder map, a shared definition of success, a monthly steering committee |
Measurable goals and KPIs
The values below are targets that we set with the client after a baseline measurement in the first phase.
| KPI | Target | How it is measured |
|---|---|---|
| WCAG 2.1 AA compliance | 0 critical errors in the audit | expert and automated audit |
| Active users of the solution | ≥ 80% of the target group after 3 months | usage telemetry |
| Service availability | ≥ 99.9% per month | synthetic monitoring, SLO |
Lessons learned and good practices
Usability tests with residents show that the biggest problem is official jargon, not technology. Handing over the code and documentation protects the contracting authority from vendor lock-in. A prototype tested with five users removes more risk than a month of discussing requirements.
Why B2B.net
B2B.net S.A. has operated since 2015 and has worked for more than 50 brands, mostly where audits are an everyday matter: in banks, insurers, and critical infrastructure. We are an accredited exam center, so a test methodology is not a declaration for us but a working standard. We deliver a first proposal of specialists within 24 hours, and a team can start within 5 business days.
Next step
Let's talk about your project. Within 24 hours we will get back to you with a quote or a proposal of engineers; a team can start within 5 business days. Contact: office@b2bnetwork.pl.
What would this look like for you?
Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.
Let's talkB2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.