The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.
In brief
- Problem
- The previous recruitment round ended with the system unavailable in the first minutes and a wave of complaints.
- Approach
- We model the traffic at the opening of the round: sign-ins within a single minute, form completion, submission.
- Goal
- p95 response time of key transactions: compliant with the SLA, e.g. ≤ 2 s; Error rate under load: < 0.1%.
Client context
Public administration is digitizing services for citizens and businesses, and the requirements for interoperability, accessibility, and security are written into law here, not just into good practice. The client is a local government unit that runs electronic recruitment rounds in which thousands of people sign in during the same minute the round opens.
Challenge
The previous recruitment round ended with the system unavailable in the first minutes and a wave of complaints. The next round has a publicly announced date.
Requirements and constraints
- The National Interoperability Framework (KRI) sets minimum requirements for the IT systems of public bodies: interoperability, security, accessibility, and internal audit. The project must leave behind documentation that lets the contracting authority pass an inspection. (source)
- WCAG 2.1/2.2 (W3C) and the Polish Digital Accessibility Act: level AA is mandatory for public bodies, and the accessibility statement must be kept up to date. Accessibility testing must combine automated tools with expert review and screen reader testing. (source)
- GDPR, i.e. Regulation (EU) 2016/679, requires data minimization, a legal basis for processing, processing agreements, and, for high-risk processing, a data protection impact assessment (DPIA). In practice it rules out copying production data into test environments without anonymization or pseudonymization. (source)
- Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, and every deliverable shipped with documentation the client's team can take over.
Approach and architecture
We run the full cycle: load tests for the forecast traffic, stress tests up to the breaking point, endurance tests that detect memory and connection leaks, and spike tests. We compare the test environment with production in a table of differences so the conclusions can be carried over, and we wire repeatable scenarios into the pipeline as performance regression tests.
We model the traffic at the opening of the round: sign-ins within a single minute, form completion, submission. We test the whole chain, including sign-in through the national node (a stub with realistic response times), and we propose a waiting room mechanism (a virtual queue).
Key elements of the solution:
- A traffic model for the opening of the round
- A sign-in node stub with realistic response times
- A virtual queue (waiting room)
- A confirmation test before the round
Team and roles
| Role | Count | Responsibility |
|---|---|---|
| Performance test engineer | 2 | load model, scripts, bottleneck analysis |
| SRE engineer | 1 | observability, SLOs, incident procedures |
| Test manager (ISTQB Advanced) | 1 | test strategy, entry and exit criteria, quality reporting |
| Product owner and domain experts (client side) | as needed | priorities, business decisions, acceptance |
Phased schedule
| Phase | Weeks | Deliverable |
|---|---|---|
| 1. Load model and criteria | 1–2 | traffic profile, SLA, test plan |
| 2. Preparing scripts and data | 3–4 | scripts, data generator, monitoring |
| 3. Test cycles and tuning | 5–8 | cycle reports, list of bottlenecks |
| 4. Confirmation test | 9–10 | SLA compliance report |
| 5. Performance regression in CI | 11–11 | automatic thresholds in the pipeline |
Technology stack
k6, Grafana, Prometheus, a virtual queue solution, CDN.
Risks and how we mitigate them
| Risk | How we mitigate it |
|---|---|
| Seasonal peaks during the project | a change freeze before the peak, performance tests against the peak profile, an on-call plan |
| Performance test environment smaller than production | an environment differences table, scaling results only where behavior is linear, a confirmation test on production in a maintenance window |
| Dependence on an external vendor and its deadlines | early agreement on API contracts, a stub environment, a weekly dependency review |
Measurable goals and KPIs
The values below are targets that we set with the client after a baseline measurement in the first phase.
| KPI | Target | How it is measured |
|---|---|---|
| p95 response time of key transactions | compliant with the SLA, e.g. ≤ 2 s | APM and test reports |
| Error rate under load | < 0.1% | load test, application logs |
| Service availability | ≥ 99.9% per month | synthetic monitoring, SLO |
Lessons learned and good practices
A virtual queue is fairer to citizens than a system that stops responding. A publicly announced date is a peak that cannot be moved, so testing has to be ready well before it. Most performance problems sit in the database and in integrations, not in the application layer.
Why B2B.net
We combine two models: we provide individual specialists and entire teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the outcome, we work at a fixed price for a defined scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies, and experience with ISO 27001, DORA, and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.
Acceptance criteria
Each phase ends with formal acceptance against criteria agreed at the start. In this engagement, acceptance covers: traffic profile, SLA, test plan; scripts, data generator, monitoring; cycle reports, list of bottlenecks; SLA compliance report; automatic thresholds in the pipeline. Final acceptance requires a KPI measurement report against the baseline, complete documentation handed over to the client's team, and a list of recommendations for the next stage, with a cost and risk assessment for each.
Next step
Want to see what such an implementation would look like in your organization? Book a 30-minute call. We will prepare a plan for the first six weeks and a team composition tailored to your system.
What would this look like for you?
Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.
Let's talkB2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.