The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.
In brief
- Problem
- The end of standard ECC support is approaching, and the current installation has hundreds of custom extensions, some of which are no longer used.
- Approach
- We choose a selective conversion path: historical data in a limited scope, with processes compared against SAP reference processes.
- Goal
- E2E processes covered by tests before go-live: 100% of critical processes; Reconciliation discrepancies between old and new system: 0 unexplained discrepancies before cutover.
Client context
The Polish banking sector is highly digitized and at the same time operates under strict supervision by the KNF (Polish Financial Supervision Authority). Every change in a system the customer uses must go through change control, testing and acceptance that can be shown to an auditor. The bank runs SAP ECC for the general ledger, fixed assets, procurement and cost controlling, with numerous ABAP extensions developed over the years.
Challenge
The end of standard ECC support is approaching, and the current installation has hundreds of custom extensions, some of which are no longer used. The bank wants to move to S/4HANA without interrupting its monthly closes.
Requirements and constraints
- End of standard SAP ECC support (2027): the vendor will end standard maintenance of the main releases of SAP ECC 6.0 at the end of 2027. Migrating to S/4HANA requires a decision on the path (greenfield, brownfield, selective) and a very large volume of process regression tests. (source)
- Recommendation D of the KNF (Polish Financial Supervision Authority) sets out the supervisor's expectations for managing information technology and the security of the ICT environment in banks: separation of environments, change control, access management and business continuity. Every change in a system must go through a testing and acceptance path that can be shown to an auditor. (source)
- DORA, Regulation (EU) 2022/2554, requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) is entered in the register of information on contracts. (source)
- KSeF (Poland's National e-Invoicing System) introduces mandatory structured invoices in the FA(3) format. Financial and accounting systems must handle sending, receiving, contingency modes and KSeF numbers throughout the document flow. (source)
- Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable supplied with documentation that the client's team can take over.
Approach and architecture
We run SAP projects according to SAP Activate: Prepare, Explore, Realize, Deploy, Run. In the Explore phase we compare processes with SAP reference processes (fit-to-standard), and every deviation needs a business justification, because every custom development is a cost at the next upgrade. We build extensions outside the core (clean core, BTP) and automate end-to-end process regression tests.
We choose a selective conversion path: historical data in a limited scope, with processes compared against SAP reference processes. Analysis of extension usage lets us retire the unused ones, and we move the necessary ones out of the core to BTP. We rehearse the migration in three trial runs with balance reconciliation.
Key elements of the solution:
- Custom code usage analysis and a catalog of items to retire
- Side-by-side extensions on SAP BTP
- Integration with banking systems through APIs instead of files
- Automated regression tests for closing processes
Team and roles
| Role | Count | Responsibility |
|---|---|---|
| Project manager | 1 | plan, budget, risks, communication with the steering committee |
| SAP consultant (FI/CO, SD, MM or PP module) | 3 | fit-to-standard, configuration, process testing |
| ABAP/BTP developer | 2 | extensions in the clean core model, integrations |
| Test analyst (ISTQB) | 2 | designing and executing test cases, reporting defects |
| Business analyst | 1 | requirements, processes, acceptance criteria |
| Product owner and domain experts (client side) | as needed | priorities, business decisions, acceptance |
Phased schedule
| Phase | Weeks | Deliverable |
|---|---|---|
| 1. Prepare and Explore (fit-to-standard) | 1–8 | gap list, project decisions |
| 2. Realize: configuration and development | 9–22 | configuration, BTP extensions |
| 3. Data migration: trial runs | 23–28 | reconciliation reports |
| 4. Integration tests and UAT | 29–36 | E2E test protocols |
| 5. Deploy and hypercare | 37–40 | cutover, post-go-live support |
Technology stack
SAP S/4HANA, SAP BTP, SAP Cloud ALM, Tricentis Tosca or SAP test automation, ABAP RAP.
Risks and how we mitigate them
| Risk | How we mitigate it |
|---|---|
| Data migration errors | data profiling, trial migrations with reconciliation, quality criteria before cutover |
| Cutover risk | at least two dress rehearsals, a rollback plan with decision criteria, a maintenance window during low traffic |
| Undocumented behavior of the old system | characterization tests (golden master) before the change, comparison of old and new results |
| Scope creep during the project | a backlog prioritized with MoSCoW, every change goes through the committee with an estimate of its impact on the deadline |
Measurable goals and KPIs
The values below are goals that we set with the client after a baseline measurement in the first phase.
| KPI | Target | How it is measured |
|---|---|---|
| E2E processes covered by tests before go-live | 100% of critical processes | test catalog |
| Reconciliation discrepancies between old and new system | 0 unexplained discrepancies before cutover | reconciliation report |
| Downtime during cutover | within the window agreed with the business | cutover plan |
Lessons learned and good practices
Analyzing how extensions are actually used usually shows that a large share of custom code is no longer needed. Base the cutover date on the closing calendar, not the project calendar. Every deviation from the SAP standard is a cost at every future upgrade.
Why B2B.net
B2B.net S.A. has operated since 2015 and has worked for more than 50 brands, mostly where audits are an everyday reality: in banks, insurance and critical infrastructure. We are an accredited exam center, so testing methodology is not a claim for us but a standard of work. We give a first proposal of specialists within 24 hours, and a team can start within 5 business days.
Next step
Facing a similar challenge? Write to office@b2bnetwork.pl or call: +48 577 317 312. You will get a first proposal of specialists or a plan for the first step within 24 hours.
What would this look like for you?