Migrating a bank's finance and controlling to SAP S/4HANA

Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
The end of standard ECC support is approaching, and the current installation has hundreds of custom extensions, some of which are no longer used.
Approach
We choose a selective conversion path: historical data in a limited scope, with processes compared against SAP reference processes.
Goal
E2E processes covered by tests before go-live: 100% of critical processes; Reconciliation discrepancies between old and new system: 0 unexplained discrepancies before cutover.

Client context

The Polish banking sector is highly digitized and at the same time operates under strict supervision by the KNF (Polish Financial Supervision Authority). Every change in a system the customer uses must go through change control, testing and acceptance that can be shown to an auditor. The bank runs SAP ECC for the general ledger, fixed assets, procurement and cost controlling, with numerous ABAP extensions developed over the years.

Challenge

The end of standard ECC support is approaching, and the current installation has hundreds of custom extensions, some of which are no longer used. The bank wants to move to S/4HANA without interrupting its monthly closes.

Requirements and constraints

  • End of standard SAP ECC support (2027): the vendor will end standard maintenance of the main releases of SAP ECC 6.0 at the end of 2027. Migrating to S/4HANA requires a decision on the path (greenfield, brownfield, selective) and a very large volume of process regression tests. (source)
  • Recommendation D of the KNF (Polish Financial Supervision Authority) sets out the supervisor's expectations for managing information technology and the security of the ICT environment in banks: separation of environments, change control, access management and business continuity. Every change in a system must go through a testing and acceptance path that can be shown to an auditor. (source)
  • DORA, Regulation (EU) 2022/2554, requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) is entered in the register of information on contracts. (source)
  • KSeF (Poland's National e-Invoicing System) introduces mandatory structured invoices in the FA(3) format. Financial and accounting systems must handle sending, receiving, contingency modes and KSeF numbers throughout the document flow. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable supplied with documentation that the client's team can take over.

Approach and architecture

We run SAP projects according to SAP Activate: Prepare, Explore, Realize, Deploy, Run. In the Explore phase we compare processes with SAP reference processes (fit-to-standard), and every deviation needs a business justification, because every custom development is a cost at the next upgrade. We build extensions outside the core (clean core, BTP) and automate end-to-end process regression tests.

We choose a selective conversion path: historical data in a limited scope, with processes compared against SAP reference processes. Analysis of extension usage lets us retire the unused ones, and we move the necessary ones out of the core to BTP. We rehearse the migration in three trial runs with balance reconciliation.

Key elements of the solution:

  • Custom code usage analysis and a catalog of items to retire
  • Side-by-side extensions on SAP BTP
  • Integration with banking systems through APIs instead of files
  • Automated regression tests for closing processes

Team and roles

RoleCountResponsibility
Project manager1plan, budget, risks, communication with the steering committee
SAP consultant (FI/CO, SD, MM or PP module)3fit-to-standard, configuration, process testing
ABAP/BTP developer2extensions in the clean core model, integrations
Test analyst (ISTQB)2designing and executing test cases, reporting defects
Business analyst1requirements, processes, acceptance criteria
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Prepare and Explore (fit-to-standard)1–8gap list, project decisions
2. Realize: configuration and development9–22configuration, BTP extensions
3. Data migration: trial runs23–28reconciliation reports
4. Integration tests and UAT29–36E2E test protocols
5. Deploy and hypercare37–40cutover, post-go-live support

Technology stack

SAP S/4HANA, SAP BTP, SAP Cloud ALM, Tricentis Tosca or SAP test automation, ABAP RAP.

Risks and how we mitigate them

RiskHow we mitigate it
Data migration errorsdata profiling, trial migrations with reconciliation, quality criteria before cutover
Cutover riskat least two dress rehearsals, a rollback plan with decision criteria, a maintenance window during low traffic
Undocumented behavior of the old systemcharacterization tests (golden master) before the change, comparison of old and new results
Scope creep during the projecta backlog prioritized with MoSCoW, every change goes through the committee with an estimate of its impact on the deadline

Measurable goals and KPIs

The values below are goals that we set with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
E2E processes covered by tests before go-live100% of critical processestest catalog
Reconciliation discrepancies between old and new system0 unexplained discrepancies before cutoverreconciliation report
Downtime during cutoverwithin the window agreed with the businesscutover plan

Lessons learned and good practices

Analyzing how extensions are actually used usually shows that a large share of custom code is no longer needed. Base the cutover date on the closing calendar, not the project calendar. Every deviation from the SAP standard is a cost at every future upgrade.

Why B2B.net

B2B.net S.A. has operated since 2015 and has worked for more than 50 brands, mostly where audits are an everyday reality: in banks, insurance and critical infrastructure. We are an accredited exam center, so testing methodology is not a claim for us but a standard of work. We give a first proposal of specialists within 24 hours, and a team can start within 5 business days.

Next step

Facing a similar challenge? Write to office@b2bnetwork.pl or call: +48 577 317 312. You will get a first proposal of specialists or a plan for the first step within 24 hours.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk

B2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.

More projects: Banking