The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.
In brief
- Problem
- A bank is planning to replace its transaction system and has no reliable picture of how the whole chain (from the mobile app through the API gateway and service bus to the core) will behave at peak load.
- Approach
- Instead of testing systems separately, we build a single load model for the entire chain based on three months of access logs.
- Goal
- p95 response time of key transactions: within the SLA, e.g. ≤ 2 s; Throughput at the peak profile: ≥ 150% of the forecast peak.
Client context
In banking, the cost of a production defect is measured not only in complaints but also in customer trust and supervisory findings. Since January 17, 2025, DORA has applied, moving the conversation about IT quality from the IT department to the board. The client is a mid-sized universal bank serving retail customers and SMEs, with online and mobile banking built on a shared service layer. Traffic is uneven: peaks on payday, at the start of the month and on the last day of tax settlements.
Challenge
The bank is planning to replace its transaction system and has no reliable picture of how the whole chain (from the mobile app through the API gateway and service bus to the core) will behave at peak load. Previous tests covered individual applications, and performance incidents only surfaced in production, most often at the interfaces between systems.
Requirements and constraints
- DORA, the Digital Operational Resilience Act (Regulation (EU) 2022/2554), requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) goes into the register of information on contractual arrangements. (source)
- Recommendation D of the KNF (Polish Financial Supervision Authority) sets out the supervisor's expectations for managing information technology and the security of the ICT environment in banks: separation of environments, change control, access management and business continuity. Every change in the system must go through a test and acceptance path that can be shown to an auditor. (source)
- GDPR, Regulation (EU) 2016/679, requires data minimization, a legal basis for processing, processing agreements and, for high-risk processing, an impact assessment (DPIA). In practice it rules out copying production data into test environments without anonymization or pseudonymization. (source)
- Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable handed over with documentation the client's team can take over.
Approach and architecture
We run the full cycle: load tests for the forecast traffic, stress tests up to the breaking point, endurance tests that detect memory and connection leaks, and spike tests. We compare the test environment with production in a table of differences so the findings can be carried over, and we plug repeatable scenarios into the pipeline as performance regression.
Instead of testing systems separately, we build a single load model for the entire chain based on three months of access logs. The scripts reproduce real customer sessions (login, balance, history, transfer, BLIK), and mocks replace only external services outside the bank's control. Each test cycle ends with an analysis session with the infrastructure and database teams, with a list of actions and their owners.
Key elements of the solution:
- Load generators in two network zones, to reproduce traffic from the internet and from the internal network
- Correlation of APM traces (OpenTelemetry) with Oracle database and queue metrics
- Mocks of external systems (BIK, KIR) with realistic latencies
- Performance regression run weekly in the pipeline
Team and roles
| Role | Count | Responsibility |
|---|---|---|
| Project manager | 1 | plan, budget, risks, communication with the steering committee |
| Test manager (ISTQB Advanced) | 1 | test strategy, entry and exit criteria, quality reporting |
| Performance test engineer | 3 | load model, scripts, bottleneck analysis |
| Database administrator | 1 | tuning, backups, schema migrations |
| SRE engineer | 1 | observability, SLOs, incident procedures |
| Product owner and domain experts (client side) | as needed | priorities, business decisions, acceptance |
Phased schedule
| Phase | Weeks | Deliverable |
|---|---|---|
| 1. Load model and criteria | 1–2 | traffic profile, SLA, test plan |
| 2. Script and data preparation | 3–6 | scripts, data generator, monitoring |
| 3. Test cycles and tuning | 7–12 | cycle reports, list of bottlenecks |
| 4. Confirmation test | 13–14 | SLA compliance report |
| 5. Performance regression in CI | 15–16 | automated thresholds in the pipeline |
Technology stack
Apache JMeter, k6, Grafana, Prometheus, Dynatrace, Oracle 19c, Kafka, Kubernetes (OpenShift), WireMock, GitLab CI.
Risks and how we mitigate them
| Risk | How we mitigate it |
|---|---|
| Performance test environment smaller than production | table of environment differences, scaling results only where the behavior is linear, confirmation test on production in a maintenance window |
| No test data free of personal data | synthetic data generator and masking that preserves referential integrity; no copying production into test |
| Test environments unavailable or unstable | environment booking schedule, virtualization of external services (mocks), daily environment smoke test |
| Service downtime during changes | blue-green or canary deployments, feature flags, maintenance windows agreed with the business |
Measurable goals and KPIs
The values below are targets that we set with the client after a baseline measurement in the first phase.
| KPI | Target | How it is measured |
|---|---|---|
| p95 response time of key transactions | within the SLA, e.g. ≤ 2 s | APM and test reports |
| Throughput at the peak profile | ≥ 150% of the forecast peak | load test |
| Error rate under load | < 0.1% | load test, application logs |
| Critical defects found after deployment | 0 critical defects in the first 30 days | production incident register |
Lessons learned and good practices
The weakest link usually sits at the interfaces between systems: in connection pools and timeouts, not in the applications themselves. DORA resilience tests and performance tests are worth planning together, because they use the same scripts and environments. Most performance problems sit in the database and in integrations, not in the application layer.
Why B2B.net
We combine two models: we provide individual engineers and whole teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the outcome, we work at a fixed price for a defined scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies and experience with ISO 27001, DORA and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.
Next step
Want to see what such an implementation would look like in your organization? Book a 30-minute call. We will prepare a plan for the first six weeks and a team composition tailored to your system.
What would this look like for you?
Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.
Let's talkB2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.