Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
A bank is planning to replace its transaction system and has no reliable picture of how the whole chain (from the mobile app through the API gateway and service bus to the core) will behave at peak load.
Approach
Instead of testing systems separately, we build a single load model for the entire chain based on three months of access logs.
Goal
p95 response time of key transactions: within the SLA, e.g. ≤ 2 s; Throughput at the peak profile: ≥ 150% of the forecast peak.

Client context

In banking, the cost of a production defect is measured not only in complaints but also in customer trust and supervisory findings. Since January 17, 2025, DORA has applied, moving the conversation about IT quality from the IT department to the board. The client is a mid-sized universal bank serving retail customers and SMEs, with online and mobile banking built on a shared service layer. Traffic is uneven: peaks on payday, at the start of the month and on the last day of tax settlements.

Challenge

The bank is planning to replace its transaction system and has no reliable picture of how the whole chain (from the mobile app through the API gateway and service bus to the core) will behave at peak load. Previous tests covered individual applications, and performance incidents only surfaced in production, most often at the interfaces between systems.

Requirements and constraints

  • DORA, the Digital Operational Resilience Act (Regulation (EU) 2022/2554), requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) goes into the register of information on contractual arrangements. (source)
  • Recommendation D of the KNF (Polish Financial Supervision Authority) sets out the supervisor's expectations for managing information technology and the security of the ICT environment in banks: separation of environments, change control, access management and business continuity. Every change in the system must go through a test and acceptance path that can be shown to an auditor. (source)
  • GDPR, Regulation (EU) 2016/679, requires data minimization, a legal basis for processing, processing agreements and, for high-risk processing, an impact assessment (DPIA). In practice it rules out copying production data into test environments without anonymization or pseudonymization. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable handed over with documentation the client's team can take over.

Approach and architecture

We run the full cycle: load tests for the forecast traffic, stress tests up to the breaking point, endurance tests that detect memory and connection leaks, and spike tests. We compare the test environment with production in a table of differences so the findings can be carried over, and we plug repeatable scenarios into the pipeline as performance regression.

Instead of testing systems separately, we build a single load model for the entire chain based on three months of access logs. The scripts reproduce real customer sessions (login, balance, history, transfer, BLIK), and mocks replace only external services outside the bank's control. Each test cycle ends with an analysis session with the infrastructure and database teams, with a list of actions and their owners.

Key elements of the solution:

  • Load generators in two network zones, to reproduce traffic from the internet and from the internal network
  • Correlation of APM traces (OpenTelemetry) with Oracle database and queue metrics
  • Mocks of external systems (BIK, KIR) with realistic latencies
  • Performance regression run weekly in the pipeline

Team and roles

RoleCountResponsibility
Project manager1plan, budget, risks, communication with the steering committee
Test manager (ISTQB Advanced)1test strategy, entry and exit criteria, quality reporting
Performance test engineer3load model, scripts, bottleneck analysis
Database administrator1tuning, backups, schema migrations
SRE engineer1observability, SLOs, incident procedures
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Load model and criteria1–2traffic profile, SLA, test plan
2. Script and data preparation3–6scripts, data generator, monitoring
3. Test cycles and tuning7–12cycle reports, list of bottlenecks
4. Confirmation test13–14SLA compliance report
5. Performance regression in CI15–16automated thresholds in the pipeline

Technology stack

Apache JMeter, k6, Grafana, Prometheus, Dynatrace, Oracle 19c, Kafka, Kubernetes (OpenShift), WireMock, GitLab CI.

Risks and how we mitigate them

RiskHow we mitigate it
Performance test environment smaller than productiontable of environment differences, scaling results only where the behavior is linear, confirmation test on production in a maintenance window
No test data free of personal datasynthetic data generator and masking that preserves referential integrity; no copying production into test
Test environments unavailable or unstableenvironment booking schedule, virtualization of external services (mocks), daily environment smoke test
Service downtime during changesblue-green or canary deployments, feature flags, maintenance windows agreed with the business

Measurable goals and KPIs

The values below are targets that we set with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
p95 response time of key transactionswithin the SLA, e.g. ≤ 2 sAPM and test reports
Throughput at the peak profile≥ 150% of the forecast peakload test
Error rate under load< 0.1%load test, application logs
Critical defects found after deployment0 critical defects in the first 30 daysproduction incident register

Lessons learned and good practices

The weakest link usually sits at the interfaces between systems: in connection pools and timeouts, not in the applications themselves. DORA resilience tests and performance tests are worth planning together, because they use the same scripts and environments. Most performance problems sit in the database and in integrations, not in the application layer.

Why B2B.net

We combine two models: we provide individual engineers and whole teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the outcome, we work at a fixed price for a defined scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies and experience with ISO 27001, DORA and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.

Next step

Want to see what such an implementation would look like in your organization? Book a 30-minute call. We will prepare a plan for the first six weeks and a team composition tailored to your system.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.