Accessibility testing of a bank's digital channels for the European Accessibility Act

Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
Since June 2025.
Approach
An expert audit of critical paths (login, transfer, account opening, loan application) with screen readers on desktop and mobile, supplemented by automated scans.
Goal
WCAG 2.1 AA conformance: 0 critical issues in the audit; Critical defects found after release: 0 critical defects in the first 30 days.

Client context

In banking, the cost of a production error is measured not only in complaints but also in customer trust and supervisory findings. DORA has applied since January 17, 2025, and it moved the conversation about IT quality from the IT department to the management board. A retail bank with online banking, a mobile app and online account opening processes.

Challenge

Since June 2025, consumer banking services must meet accessibility requirements. The bank does not know how many screens have problems, and product teams lack the skills to test with assistive technologies.

Requirements and constraints

  • The European Accessibility Act (Directive 2019/882) and the Polish act on ensuring compliance with accessibility requirements have covered, since June 28, 2025, consumer banking, e-commerce and communication services, among others. Digital channels must meet accessibility requirements, and failing to do so risks penalties and inspections by the market surveillance authority. (source)
  • WCAG 2.1/2.2 (W3C) and the Polish act on digital accessibility: for public entities, level AA is mandatory, and the accessibility statement must be up to date. Accessibility testing must combine automated tools with expert evaluation and screen reader testing. (source)
  • Recommendation D of the KNF (Polish Financial Supervision Authority) sets out the supervisor's expectations for managing information technology and the security of the ICT environment in banks: separation of environments, change control, access management and business continuity. Every change in a system must go through a testing and acceptance path that can be shown to an auditor. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable supplied with documentation that the client's team can take over.

Approach and architecture

We start with a risk-based test strategy: together with process owners we assess the likelihood and impact of failure in each area, and the result determines the depth of testing. Test cases are designed by ISTQB-certified analysts, and every defect gets a root cause classification, so after a few sprints it is clear where most errors originate and what to improve in the development process.

An expert audit of critical paths (login, transfer, account opening, loan application) with screen readers on desktop and mobile, supplemented by automated scans. Findings go into a prioritized backlog, and teams get a library of accessible components and automated accessibility tests in the pipeline, so new screens do not introduce regressions.

Key elements of the solution:

  • WCAG 2.1 AA audit of critical paths
  • Testing with NVDA, JAWS, VoiceOver and TalkBack
  • Automated axe tests in the pipeline
  • Training for designers and developers

Team and roles

RoleCountResponsibility
Test manager (ISTQB Advanced)1test strategy, entry and exit criteria, quality reporting
Test analyst (ISTQB)3designing and executing test cases, reporting defects
UX/UI designer1research, prototypes, usability and accessibility testing
Test automation engineer1framework, scripts, CI integration
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Analysis and test strategy1–3test strategy, risk matrix, environment plan
2. Test case design4–7test case repository with traceability
3. System and integration testing8–14daily reports, defect register
4. Acceptance testing (UAT) with the business15–18UAT protocols, exit criteria
5. Closure report and handover19–20quality report, recommendations

Technology stack

axe-core, Lighthouse, NVDA, JAWS, VoiceOver, TalkBack, Playwright.

Risks and how we mitigate them

RiskHow we mitigate it
Non-compliance with accessibility requirementsscreen reader testing in every sprint, components accessible by design, an expert audit before release
Low user adoptionambassadors in departments, training on users' own cases, measuring usage from day one
Scope creep during the projecta backlog prioritized with MoSCoW, every change goes through the committee with an estimate of its impact on the deadline

Measurable goals and KPIs

The values below are goals that we set with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
WCAG 2.1 AA conformance0 critical issues in the auditexpert and automated audit
Critical defects found after release0 critical defects in the first 30 daysproduction incident register

Lessons learned and good practices

Most accessibility problems originate in a few shared components, so fixing them improves hundreds of screens at once. Testing with real assistive technologies finds problems that automated tools do not see. Traceability from requirements to tests is cheap when you build it from day one, and very expensive when you reconstruct it before an audit.

Why B2B.net

We combine two models: we provide individual specialists and whole teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the result, we work at a fixed price for a defined scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies, and experience with ISO 27001, DORA and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.

Next step

Want to see how such a project would look in your organization? Book a 30-minute call. We will prepare a plan for the first six weeks and a team lineup matched to your system.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk

B2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.

More projects: Banking