The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.
In brief
- Problem
- The migration covers products that work differently in the two banks: different interest calculation methods, schedules and fees.
- Approach
- We run migration tests on three levels: technical completeness (record counts, checksums), mapping correctness (product by product, with decision tables for exceptions) and business continuity (interest and schedules calculated in both systems for the same dates).
- Goal
- Reconciliation discrepancies between old and new system: 0 unexplained discrepancies before cutover; Critical defects found after release: 0 critical defects in the first 30 days.
Client context
The Polish banking sector is highly digitized and at the same time operates under strict supervision by the KNF (Polish Financial Supervision Authority). Every change in a system the customer uses must go through change control, testing and acceptance that can be shown to an auditor. A universal bank is acquiring a smaller retail bank and moving its customers, accounts, loans and deposits to its own systems.
Challenge
The migration covers products that work differently in the two banks: different interest calculation methods, schedules and fees. A customer of the acquired bank must not notice any change in their balance, repayment schedule or access to online banking.
Requirements and constraints
- Recommendation D of the KNF (Polish Financial Supervision Authority) sets out the supervisor's expectations for managing information technology and the security of the ICT environment in banks: separation of environments, change control, access management and business continuity. Every change in a system must go through a testing and acceptance path that can be shown to an auditor. (source)
- GDPR, Regulation (EU) 2016/679, requires data minimization, a legal basis for processing and data processing agreements, and, for high-risk processing, a data protection impact assessment (DPIA). In practice it rules out copying production data to test environments without anonymization or pseudonymization. (source)
- DORA, Regulation (EU) 2022/2554, requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) is entered in the register of information on contracts. (source)
- Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable supplied with documentation that the client's team can take over.
Approach and architecture
We work with an ISTQB-based test process: test basis analysis, test case design with black-box techniques (equivalence classes, boundary values, decision tables, state transitions), and then execution with full traceability to requirements. Test priority comes from product risk analysis, not from the order in the specification: we first check what hurts the customer and the supervisor when it stops working.
We run migration tests on three levels: technical completeness (record counts, checksums), mapping correctness (product by product, with decision tables for exceptions) and business continuity (interest and schedules calculated in both systems for the same dates). Every trial migration ends with a discrepancy report that product owners approve.
Key elements of the solution:
- Automated record-by-record reconciliation of balances and schedules
- Comparison of interest calculations in both systems on selected dates
- Customer samples for end-to-end tests in the channels
- Discrepancy report with root cause categories
Team and roles
| Role | Count | Responsibility |
|---|---|---|
| Test manager (ISTQB Advanced) | 1 | test strategy, entry and exit criteria, quality reporting |
| Test analyst (ISTQB) | 4 | designing and executing test cases, reporting defects |
| Data engineer | 1 | pipelines, data model, data quality tests |
| Business analyst | 2 | requirements, processes, acceptance criteria |
| Product owner and domain experts (client side) | as needed | priorities, business decisions, acceptance |
Phased schedule
| Phase | Weeks | Deliverable |
|---|---|---|
| 1. Analysis and test strategy | 1–4 | test strategy, risk matrix, environment plan |
| 2. Test case design | 5–10 | test case repository with traceability |
| 3. System and integration testing | 11–20 | daily reports, defect register |
| 4. Acceptance testing (UAT) with the business | 21–26 | UAT protocols, exit criteria |
| 5. Closure report and handover | 27–30 | quality report, recommendations |
Technology stack
SQL, Python (pandas) for reconciliation, Jira Xray, Power BI.
Risks and how we mitigate them
| Risk | How we mitigate it |
|---|---|
| Data migration errors | data profiling, trial migrations with reconciliation, quality criteria before cutover |
| Cutover risk | at least two dress rehearsals, a rollback plan with decision criteria, a maintenance window during low traffic |
| Undocumented behavior of the old system | characterization tests (golden master) before the change, comparison of old and new results |
| Diverging stakeholder expectations | stakeholder map, a shared definition of success, a monthly steering committee |
Measurable goals and KPIs
The values below are goals that we set with the client after a baseline measurement in the first phase.
| KPI | Target | How it is measured |
|---|---|---|
| Reconciliation discrepancies between old and new system | 0 unexplained discrepancies before cutover | reconciliation report |
| Critical defects found after release | 0 critical defects in the first 30 days | production incident register |
| Downtime during cutover | within the window agreed with the business | cutover plan |
Lessons learned and good practices
Differences in interest rounding only show up when you compare across many dates. A single test date is not enough. Product owners must approve discrepancies, otherwise the test team becomes the arbiter of business decisions. Exit criteria agreed before testing starts save weeks of disputes at the end of the project.
Why B2B.net
B2B.net S.A. has operated since 2015 and has worked for more than 50 brands, mostly where audits are an everyday reality: in banks, insurance and critical infrastructure. We are an accredited exam center, so testing methodology is not a claim for us but a standard of work. We give a first proposal of specialists within 24 hours, and a team can start within 5 business days.
Next step
Let's talk about your project. Within 24 hours we will get back to you with a quote or a proposal of engineers; a team can start within 5 business days. Contact: office@b2bnetwork.pl.
What would this look like for you?
Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.
Let's talkB2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.