Core banking modernization: migration strategies and their risks

B2Bnetwork team · · 6 min

IT in banking

In brief

A core banking system can be replaced in four ways: with a single cutover (big bang), in phases by product or customer, by building a new core alongside the old one, or by gradually decommissioning the old system behind an API layer. Phased approaches are usually the least risky, but they require a long period in which two systems run in parallel and have to be reconciled. The choice depends not only on technology, but also on the number of integrations, data quality, and how long the bank can bear double maintenance.

What exactly gets replaced in a core banking system

A core banking system maintains accounts, posts transactions, calculates interest and fees, and closes the day. Around it run dozens of systems: online and mobile banking, the card system, payments, loans, the data warehouse, reporting to the regulator, AML. In many banks the core is decades old, and its logic lives in COBOL, RPG, or PL/SQL code whose authors no longer work at the company.

That is why modernization is rarely the replacement of a single program. It is a rebuild of a network of dependencies: every integration, every report, and every nightly process that reads data from the core must work the same way, or differently by design. Before choosing a strategy, the bank should have a map of these dependencies, not just a list of the new system's features. If the old core runs on a mainframe or IBM i, the articles Mainframe in a bank and IBM i modernization will also be useful.

Four migration strategies

StrategyHow it worksMain risk
Big bangAll products and customers move over a single weekendAn error hits everyone at once, and rollback is hard
PhasedOne product first (e.g. term deposits), then the next ones or successive customer groupsA long period of two systems coexisting and balances being reconciled
New core alongside the old oneNew customers and products go straight to the new system, existing ones stayTwo systems for years, with the migration of existing customers postponed indefinitely
Gradual decommissioningAn API layer takes over traffic, and functions are moved one at a time (the "strangler fig" pattern)The intermediate layer itself becomes a complex system

Big bang

Big bang has one advantage: you maintain two systems only briefly. It works in smaller banks with a simple offering, or when merging two banks, where one system has to disappear anyway. It requires several full trial migrations on a copy of production data and a rollback plan that someone has actually rehearsed. You also have to honestly work out what happens if the error shows up only on Monday morning, when customers have already made thousands of transactions in the new system and going back to the old one means moving them back.

Phased migration and gradual decommissioning

Phased migration and decommissioning behind an API layer spread the risk over time. Each phase is smaller, so it is easier to test and roll back. The price is a period in which part of the data lives in the old system and part in the new one. Reports, the data warehouse, and customer service then have to see a single view of the customer, even though the data comes from two sources.

Risks that come back in every program

Whatever the strategy, the same problems appear in most core replacement programs:

  • Hidden logic. The old system calculates interest, rounds amounts, or handles exceptions in a way that no document describes. It only comes out when the results are compared.
  • Data quality. Records from the 1990s have empty fields, outdated codes, and duplicate customers. Migration exposes what the old system tolerated.
  • The cutover window. Banking does not tolerate interruptions. Every hour of unavailability means customers without access to their money, so the plan must fit within a window the bank will accept.
  • Performance. The new system behaves differently under load, especially at day-end close and when calculating interest for all accounts.
  • Regulation. Changing a key system touches ICT risk management under DORA, vendor contracts, and business continuity plans.

Most of these risks share a common source: a collision with real data that comes too late. A program that does its first migration on a copy of production a month before the deadline discovers hidden logic and data errors when there is no time left to fix them. That is why it is worth starting trial migrations and comparison tests as early as possible, even on an incomplete version of the new system, and repeating them regularly until the cutover.

How to prepare the first migration

A bank starting with the first phase should choose a product that is simple but real, for example term deposits or savings accounts. A "trial" product that nobody uses will prove nothing.

  1. List the dependencies. Every system that reads or writes core data gets an owner and a plan: repointing, an adapter, or shutdown.
  2. Define the reconciliations. Decide which checksums you compare after the migration: number of accounts, balances, interest accrued, transaction history.
  3. Rehearse the migration at least several times. Each trial on a copy of the data gives you the duration, a list of rejected records, and a list of differences.
  4. Set the cutover and rollback criteria. Who makes the decision, based on which results, and until what hour you can still return to the old system.

We describe the details of moving data without interrupting service in the article Migrating customer data without service interruption.

Testing as a condition of cutover

In a core replacement program, testing is not a phase at the end of the schedule but a condition of every cutover decision. The most errors are caught by comparison tests: the same transactions pass through the old and the new system, and differences in balances, interest, and fees go to analysis. In addition there are integration tests with every system on the dependency map, performance tests of the day-end close at full volume, and regression tests of the channels customers use.

A rule that works well is that no phase goes to production without a signed reconciliation report and without a performance test on production-scale data. This is how B2Bnetwork engineers work in the performance testing of banking before a core migration.

Questions and answers

Which core banking replacement strategy is the safest?

Phased migration and gradual decommissioning of the old system carry the smallest single risk, because each step is small and can be rolled back. They are not safe by definition, however: a long period of two systems coexisting requires continuous data reconciliation and double maintenance. Big bang can be reasonable in a small bank with a simple offering, or when merging two banks.

How many trial migrations are needed?

As many as it takes for two consecutive trials to give a repeatable duration and show no new differences in reconciliations. In practice this is usually several full trials on a copy of production data. A single trial proves nothing, because it only shows that the migration worked once.

Can the core be replaced without interrupting access to banking?

Usually not entirely without interruption, but it can be shortened to a few hours at night or on a weekend. Phased migration, replication of changes from the database during the window, and a read-only mode for customer channels during the cutover all help. The key is to rehearse the whole plan on a copy of the data.

Who should decide on the cutover to the new system?

The program committee makes the decision, but on the basis of criteria set in advance: the balance reconciliation report, the results of regression and performance tests, and the list of open critical defects. If the criteria are written down before the migration weekend, the decision at night is quick and does not depend on schedule pressure.

What it looks like in a project