SAP S/4HANA implementation in a plant's production and internal logistics

Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
Production planning happens in spreadsheets, and the ERP is used mainly for bookkeeping.
Approach
We implement S/4HANA in the PP, MM, SD, and FI/CO modules with a fit-to-standard approach.
Goal
E2E processes covered by tests before go-live: 100% of critical processes; Reconciliation discrepancies between the old and new system: 0 unexplained discrepancies before cutover.

Client context

Industrial plants connect the IT world with the OT world: controllers, SCADA, and MES systems run for years, and every line stoppage costs money. Software changes must respect the rhythm of production. The client is a metal products manufacturer with one large plant, currently on an older ERP system with many auxiliary spreadsheets in production planning.

Challenge

Production planning happens in spreadsheets, and the ERP is used mainly for bookkeeping. The lack of reliable information on stock levels and work in progress causes excess inventory and delivery delays.

Requirements and constraints

  • End of standard support for SAP ECC (2027): the vendor will end standard maintenance of the main SAP ECC 6.0 releases at the end of 2027. Migrating to S/4HANA requires a decision on the path (greenfield, brownfield, selective) and a very large volume of process regression tests. (source)
  • KSeF (Poland's National e-Invoicing System) introduces mandatory structured invoices in the FA(3) format. Finance and accounting systems must handle sending, receiving, fallback modes, and KSeF numbers throughout the document flow. (source)
  • NIS2, i.e. Directive (EU) 2022/2555, and the amendment to the Polish National Cybersecurity System Act (KSC) require essential and important entities to implement cybersecurity risk management measures, supply chain security, and incident reporting within short deadlines (an early warning within 24 hours). The management board is personally accountable, so documenting decisions is part of the product. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, and every element delivered with documentation that the client's team can take over.

Approach and architecture

We run SAP projects following SAP Activate: Prepare, Explore, Realize, Deploy, Run. In the Explore phase we compare processes with SAP's reference processes (fit-to-standard), and every deviation needs a business justification, because every custom development is a cost at the next upgrade. We build extensions outside the core (clean core, BTP) and automate end-to-end process regression tests.

We implement S/4HANA in the PP, MM, SD, and FI/CO modules with a fit-to-standard approach. We replace planning spreadsheets with MRP planning, using master data cleaned before migration. Production is recorded on terminals at the lines, not in the office at the end of the shift.

Key elements of the solution:

  • PP/MM/SD/FI-CO configuration that follows the standard
  • Cleaned master data: material numbers, routings, BOMs
  • Production recording terminals
  • Integration with the quality system and scales

Team and roles

RoleCountResponsibility
Project manager1plan, budget, risks, communication with the steering committee
SAP consultant (FI/CO, SD, MM, or PP module)4fit-to-standard, configuration, process testing
ABAP/BTP developer1extensions in the clean core model, integrations
Test analyst (ISTQB)2designing and running test cases, reporting defects
Business analyst1requirements, processes, acceptance criteria
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Prepare and Explore (fit-to-standard)1–9gap list, design decisions
2. Realize: configuration and development10–24configuration, BTP extensions
3. Data migration: trial runs25–31reconciliation reports
4. Integration testing and UAT32–40E2E test protocols
5. Deploy and hypercare41–44cutover, post-deployment support

Technology stack

SAP S/4HANA, SAP Fiori, SAP BTP, SAP Cloud ALM, industrial terminals.

Risks and how we mitigate them

RiskHow we mitigate it
Errors in data migrationdata profiling, trial migrations with reconciliation, quality criteria before cutover
Cutover riskat least two dress rehearsals, a rollback plan with decision criteria, a maintenance window during low traffic
Low adoption by usersambassadors in departments, training on their own cases, measuring usage from day one
Scope creep during the projecta backlog with MoSCoW priorities, every change goes through the committee with an estimate of its impact on the schedule

Measurable goals and KPIs

The values below are targets that we set with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
E2E processes covered by tests before go-live100% of critical processestest catalog
Reconciliation discrepancies between the old and new system0 unexplained discrepancies before cutoverreconciliation report
Downtime during cutoverwithin the window agreed with the businesscutover plan
Active users of the solution≥ 80% of the target group after 3 monthsusage telemetry

Lessons learned and good practices

The quality of master data (routings, BOMs) decides whether MRP produces a reliable plan. Recording production at the line is a condition for real information on work in progress. Every deviation from the SAP standard is a cost at every future upgrade.

Why B2B.net

B2B.net S.A. has operated since 2015 and has worked for more than 50 brands, mostly where audit is an everyday matter: in banks, insurance, and critical infrastructure. We are an accredited exam center, so testing methodology is not a claim for us but a working standard. We give a first proposal of specialists within 24 hours, and a team can start within 5 business days.

Next step

Have a similar challenge? Write to office@b2bnetwork.pl or call: +48 577 317 312. You will get a first proposal of specialists or a plan for the first step within 24 hours.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk

B2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.

More projects: Manufacturing