An OT security program for an operator of wind and photovoltaic farms

Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
The farms are connected to the control room over various links, and turbine and inverter vendors have their own remote access channels.
Approach
An inventory of assets and connections at every farm, a model of zones and conduits, a central remote access point for vendors, and OT traffic monitoring.
Goal
Closed compliance gaps: 100% of critical gaps before the supervisory deadline; Time from detection to initial notification of a major incident: within the regulatory deadline (e.g. 4 h/24 h).

Client context

Energy companies are essential entities under NIS2 and the Polish National Cybersecurity System Act (KSC), and at the same time they must implement market changes imposed by national and EU regulations. The client is the owner and operator of a dozen or so wind and photovoltaic farms managed from a central control room.

Challenge

The farms are connected to the control room over various links, and turbine and inverter vendors have their own remote access channels. The company is becoming an essential entity under NIS2.

Requirements and constraints

  • NIS2, that is Directive (EU) 2022/2555, and the amendment to the KSC Act require essential and important entities to implement cybersecurity risk management measures and supply chain security, and to report incidents within short deadlines (early warning within 24 hours). The management board is personally liable, so documenting decisions is part of the product. (source)
  • The Polish National Cybersecurity System Act defines the obligations of operators of essential services, including incident handling, cooperation with CSIRT, and security audits every two years. The project must provide for an incident reporting procedure and audit trails. (source)
  • IEC 62443 (security of industrial automation systems) divides an installation into zones and conduits, defines security levels (SL), and sets requirements for component vendors. Every IT–OT connection must pass through a controlled conduit. (source)
  • REMIT, that is Regulation (EU) 1227/2011 (amended by 2024/1106), requires reporting of transactions on the wholesale energy market and publication of inside information. Data must be complete, and reports must be sent by the deadlines required by ACER. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, and every deliverable shipped with documentation that the client's team can take over.

Approach and architecture

We run the compliance program like a product project: a map from requirements to controls, from controls to evidence, and from evidence to systems. Wherever possible we replace manual spreadsheets with automated reports (access reviews, asset inventory, patch status), and we rehearse incident scenarios with the management board, because the regulations require its real involvement.

An inventory of assets and connections at every farm, a model of zones and conduits, a central remote access point for vendors, and OT traffic monitoring. We rehearse incident procedures with the control room.

Key elements of the solution:

  • An inventory of assets and connections per farm
  • Zones and conduits according to IEC 62443
  • Central vendor access with session recording
  • OT traffic monitoring and SOC integration

Team and roles

RoleCountResponsibility
Security architect1threat model, security requirements, design reviews
SOC analyst1detection rules, alert handling, playbooks
Compliance specialist1requirements map, documentation, compliance evidence
Project manager1plan, budget, risks, communication with the steering committee
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Gap analysis and risk assessment1–5gap report, risk register
2. Framework and documentation design6–10policies, procedures, registers
3. Implementing technical controls11–18controls, evidence automation
4. Exercises and testing19–22incident exercises, resilience tests
5. Internal audit and maintenance plan23–24audit report, compliance calendar

Technology stack

Passive OT monitoring, industrial firewalls, PAM, SIEM, VPN with MFA.

Risks and how we mitigate them

RiskHow we mitigate it
Impact of IT changes on production continuity (OT)tests on a rig that reproduces the line, changes only during downtime windows, zones and conduits per IEC 62443
Unknown systems and accounts (shadow IT)inventory from tools and interviews, an asset register, central identity management
Dependence on an external vendor and its deadlinesearly agreement on API contracts, a stub environment, a weekly dependency review

Measurable goals and KPIs

The values below are targets that we agree with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
Closed compliance gaps100% of critical gaps before the supervisory deadlinecompliance backlog
Time from detection to initial notification of a major incidentwithin the regulatory deadline (e.g. 4 h/24 h)exercises and incident register
Accounts with multi-factor authentication100% of accountsidentity console

Lessons learned and good practices

Vendor remote access is one of the biggest risks in distributed energy. Incident exercises with the control room reveal gaps in communication with vendors. Management board involvement has to be scheduled in the calendar, not left to chance.

Why B2B.net

We combine two models: we supply individual specialists and whole teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the outcome, we work at a fixed price per scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies, and experience with ISO 27001, DORA, and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.

Next step

Want to see what such a deployment would look like in your organization? Book a 30-minute call. We will prepare a plan for the first six weeks and a team composition matched to your system.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk

B2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.

More projects: Energy