The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.
In brief
- Problem
- The farms are connected to the control room over various links, and turbine and inverter vendors have their own remote access channels.
- Approach
- An inventory of assets and connections at every farm, a model of zones and conduits, a central remote access point for vendors, and OT traffic monitoring.
- Goal
- Closed compliance gaps: 100% of critical gaps before the supervisory deadline; Time from detection to initial notification of a major incident: within the regulatory deadline (e.g. 4 h/24 h).
Client context
Energy companies are essential entities under NIS2 and the Polish National Cybersecurity System Act (KSC), and at the same time they must implement market changes imposed by national and EU regulations. The client is the owner and operator of a dozen or so wind and photovoltaic farms managed from a central control room.
Challenge
The farms are connected to the control room over various links, and turbine and inverter vendors have their own remote access channels. The company is becoming an essential entity under NIS2.
Requirements and constraints
- NIS2, that is Directive (EU) 2022/2555, and the amendment to the KSC Act require essential and important entities to implement cybersecurity risk management measures and supply chain security, and to report incidents within short deadlines (early warning within 24 hours). The management board is personally liable, so documenting decisions is part of the product. (source)
- The Polish National Cybersecurity System Act defines the obligations of operators of essential services, including incident handling, cooperation with CSIRT, and security audits every two years. The project must provide for an incident reporting procedure and audit trails. (source)
- IEC 62443 (security of industrial automation systems) divides an installation into zones and conduits, defines security levels (SL), and sets requirements for component vendors. Every IT–OT connection must pass through a controlled conduit. (source)
- REMIT, that is Regulation (EU) 1227/2011 (amended by 2024/1106), requires reporting of transactions on the wholesale energy market and publication of inside information. Data must be complete, and reports must be sent by the deadlines required by ACER. (source)
- Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, and every deliverable shipped with documentation that the client's team can take over.
Approach and architecture
We run the compliance program like a product project: a map from requirements to controls, from controls to evidence, and from evidence to systems. Wherever possible we replace manual spreadsheets with automated reports (access reviews, asset inventory, patch status), and we rehearse incident scenarios with the management board, because the regulations require its real involvement.
An inventory of assets and connections at every farm, a model of zones and conduits, a central remote access point for vendors, and OT traffic monitoring. We rehearse incident procedures with the control room.
Key elements of the solution:
- An inventory of assets and connections per farm
- Zones and conduits according to IEC 62443
- Central vendor access with session recording
- OT traffic monitoring and SOC integration
Team and roles
| Role | Count | Responsibility |
|---|---|---|
| Security architect | 1 | threat model, security requirements, design reviews |
| SOC analyst | 1 | detection rules, alert handling, playbooks |
| Compliance specialist | 1 | requirements map, documentation, compliance evidence |
| Project manager | 1 | plan, budget, risks, communication with the steering committee |
| Product owner and domain experts (client side) | as needed | priorities, business decisions, acceptance |
Phased schedule
| Phase | Weeks | Deliverable |
|---|---|---|
| 1. Gap analysis and risk assessment | 1–5 | gap report, risk register |
| 2. Framework and documentation design | 6–10 | policies, procedures, registers |
| 3. Implementing technical controls | 11–18 | controls, evidence automation |
| 4. Exercises and testing | 19–22 | incident exercises, resilience tests |
| 5. Internal audit and maintenance plan | 23–24 | audit report, compliance calendar |
Technology stack
Passive OT monitoring, industrial firewalls, PAM, SIEM, VPN with MFA.
Risks and how we mitigate them
| Risk | How we mitigate it |
|---|---|
| Impact of IT changes on production continuity (OT) | tests on a rig that reproduces the line, changes only during downtime windows, zones and conduits per IEC 62443 |
| Unknown systems and accounts (shadow IT) | inventory from tools and interviews, an asset register, central identity management |
| Dependence on an external vendor and its deadlines | early agreement on API contracts, a stub environment, a weekly dependency review |
Measurable goals and KPIs
The values below are targets that we agree with the client after a baseline measurement in the first phase.
| KPI | Target | How it is measured |
|---|---|---|
| Closed compliance gaps | 100% of critical gaps before the supervisory deadline | compliance backlog |
| Time from detection to initial notification of a major incident | within the regulatory deadline (e.g. 4 h/24 h) | exercises and incident register |
| Accounts with multi-factor authentication | 100% of accounts | identity console |
Lessons learned and good practices
Vendor remote access is one of the biggest risks in distributed energy. Incident exercises with the control room reveal gaps in communication with vendors. Management board involvement has to be scheduled in the calendar, not left to chance.
Why B2B.net
We combine two models: we supply individual specialists and whole teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the outcome, we work at a fixed price per scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies, and experience with ISO 27001, DORA, and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.
Next step
Want to see what such a deployment would look like in your organization? Book a 30-minute call. We will prepare a plan for the first six weeks and a team composition matched to your system.
What would this look like for you?
Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.
Let's talkB2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.