In brief
An entity covered by NIS2 reports a significant incident in three steps: an early warning within 24 hours, an incident notification within 72 hours of becoming aware, and a final report no later than one month after the notification (Article 23). A financial entity covered by DORA reports major ICT-related incidents to the supervisory authority, also in three stages, with deadlines set in technical standards. A personal data breach may additionally require a report to UODO (the Polish Data Protection Authority) within 72 hours (Article 33 GDPR).
Which regime applies to your company
The first question for any incident is: under which rules do we assess it. The answer is worth writing into the procedure before anything happens.
- A financial entity covered by DORA (bank, insurer, payment institution, investment firm) assesses ICT-related incidents under DORA. Article 4 of NIS2 gives precedence to a sector-specific act, so the NIS2 reporting obligation does not apply to it in that area.
- An essential or important entity under NIS2 (telecom operator, energy company, hospital, managed service provider, manufacturing plant) reports significant incidents under Article 23 of NIS2 and national law.
- Every personal data controller additionally assesses whether the incident is a personal data breach within the meaning of the GDPR.
So one incident can trigger two reports: for example, a ransomware attack on a hospital is an incident under NIS2 and usually a data breach under the GDPR.
NIS2: three stages and deadlines
Article 23 concerns significant incidents, meaning those that have caused or can cause severe operational disruption of services or financial loss, or that have affected or can affect other persons by causing considerable material or non-material damage.
| Stage | Deadline | Content |
|---|---|---|
| Early warning | without undue delay, within 24 h of becoming aware | whether the incident may have been caused by unlawful or malicious action and whether it could have a cross-border impact |
| Incident notification | within 72 h of becoming aware | update of the information, initial assessment of severity and impact, indicators of compromise where available |
| Intermediate report | on request of the CSIRT or authority | current status |
| Final report | no later than one month after the incident notification | detailed description, type of threat or root cause, mitigation applied, cross-border impact |
If the incident is still ongoing at the deadline for the final report, the entity submits a progress report, and the final report within one month of the incident being handled. Reports go to the CSIRT or the competent authority, depending on national law. The entity also informs the recipients of its services when the incident may adversely affect the provision of the service.
DORA: a major incident and three reports
DORA requires classification first. Article 18 lists the criteria, including the number of clients and counterparts affected, the duration and downtime of services, geographical spread, data losses, the criticality of the affected services and economic impact. The thresholds at which an incident becomes major are set in the regulatory technical standards.
A major ICT-related incident is reported to the competent authority (Article 19) in three stages:
- An initial notification.
- An intermediate report, when the status changes or new information appears.
- A final report, when the root cause analysis is complete.
The deadlines for each stage and the form templates are set in the regulatory and implementing technical standards issued under Article 20, and the team should copy the hours into the procedure from there. When an incident affects the financial interests of clients, the entity informs them without undue delay about the incident and the measures taken (Article 19(3)). Significant cyber threats may be reported voluntarily.
Side by side in one table
| DORA | NIS2 | GDPR | |
|---|---|---|---|
| Who it applies to | financial entities | essential and important entities | data controllers |
| What is reported | major ICT-related incident | significant incident | personal data breach |
| To whom | competent authority (financial supervisor) | CSIRT or competent authority | supervisory authority (in Poland, UODO) |
| Stages | initial, intermediate, final | early warning, notification, final | one report, supplemented as facts are established |
| Deadlines | in the technical standards | 24 h, 72 h, 1 month | where feasible within 72 h of becoming aware of the breach |
Article 33 of the GDPR requires a report without undue delay and, where feasible, within 72 hours, unless the breach is unlikely to result in a risk to the rights and freedoms of individuals. Where the risk is high, the controller also notifies the data subjects (Article 34).
One process instead of three
What works best is a single incident handling procedure with decision points, not three separate documents. This layout works:
- Detection and time stamp. Deadlines run from becoming aware of the incident, so the ticketing system records the moment the incident was classified as potentially reportable.
- Classification. One card with the DORA or NIS2 criteria and a question about personal data. The on-call incident manager answers it, not a committee.
- Prepared templates. Forms with the entity's fixed data filled in beforehand, so that at night only the description needs to be added.
- Roles and deputies. Who signs the report, who talks to the supervisor, who informs customers. Two people for every role.
- Exercises. At least once a year, an exercise on a scenario, for example a cloud provider outage on a Friday evening.
After every incident, including unreported ones, a short review is worthwhile: was the classification accurate, how much time passed between detection and decision, did the templates have all the required fields. Conclusions go into the procedure, and recurring causes into the test plan and vulnerability remediation. The DORA final report and the NIS2 final report both require root cause analysis anyway, so the review is not extra work.
Without good telemetry you cannot assess the scale of an incident within hours, so the procedure relies on logs, metrics and traces (see Observability: logs, metrics and traces in a distributed system). Detection rules and response scenarios at a bank are shown in the security operations center scenario. Restoring services after an incident is described in the article Business continuity: BCP and DRP for critical systems, and the scope of obligations for NIS2 entities in NIS2: who it covers and what it requires from IT.
Questions and answers
Does a bank report an incident under both DORA and NIS2?
Not in the area that DORA regulates. Article 4 of NIS2 provides that where a sector-specific act imposes at least equivalent reporting obligations, the relevant NIS2 provisions do not apply. A bank reports major ICT-related incidents under DORA, and personal data breaches separately under the GDPR.
When does the reporting clock start?
Under NIS2 and the GDPR, from becoming aware of the incident or breach, not from when it began. So the procedure should state clearly who determines, and on what basis, that an incident is significant, and record that moment. Under DORA, the starting point and deadlines are set by the technical standards.
Do I have to report an incident at a supplier too?
Yes, if it meets the criteria on your side. A cloud provider outage that stops your online banking is your incident, and you classify and report it. The contract with the supplier should require prompt information and help with the incident, which Article 30 of DORA requires for ICT contracts.
Is a personal data leak also an incident under DORA?
It can be. Data loss is one of the classification criteria in Article 18 of DORA, so the same leak can be both a major ICT-related incident and a personal data breach. The entity then files two reports: to the financial supervisor and to UODO, each under its own deadlines.