Test management in a claims system replacement program

Project write-up

The client is described by industry and scale, without a name. KPI figures are targets agreed with the client after a baseline measurement.

In brief

Problem
The vendor tests its own product, but nobody is responsible for testing the insurer's end-to-end processes, and different teams test in different tools.
Approach
We take over the role of program test manager: one test strategy for all workstreams, a shared tool, shared entry and exit criteria, and a weekly readiness report based on data rather than declarations.
Goal
Defect detection effectiveness (DDE): ≥ 90%; Critical defects found after release: 0 critical defects in the first 30 days.

Client context

The insurance market in Poland is shifting sales to digital channels and bancassurance, which requires integration with partners and consistent customer service across many channels. A property and casualty insurer implementing a standard claims system from a foreign vendor, with integrations to the policy, finance and payment systems and the customer portal.

Challenge

The vendor tests its own product, but nobody is responsible for testing the insurer's end-to-end processes, and different teams test in different tools. The steering committee has no reliable information on whether the system is ready.

Requirements and constraints

  • The IDD directive and the Polish act on insurance distribution regulate needs assessment, delivery of documents (KID/IPID) and management of conflicts of interest in distribution. A digital sales path must leave a trail that can be reconstructed when a complaint is filed. (source)
  • GDPR, Regulation (EU) 2016/679, requires data minimization, a legal basis for processing and data processing agreements, and, for high-risk processing, a data protection impact assessment (DPIA). In practice it rules out copying production data to test environments without anonymization or pseudonymization. (source)
  • DORA, Regulation (EU) 2022/2554, requires ICT risk management, a register of contracts with ICT providers, classification and reporting of major incidents, and regular testing of operational resilience. For the project this means every new component needs an owner, a dependency map and a resilience test scenario, and the provider (including us) is entered in the register of information on contracts. (source)
  • Solvency II and the KNF (Polish Financial Supervision Authority) guidelines for insurance undertakings require data quality for calculating reserves and capital, documented data lineage and control over models. The data warehouse and reporting must pass validation by the actuarial function. (source)
  • Project constraints: work only on anonymized or synthetic data outside production, access to systems through the client's infrastructure, every deliverable supplied with documentation that the client's team can take over.

Approach and architecture

We start with a risk-based test strategy: together with process owners we assess the likelihood and impact of failure in each area, and the result determines the depth of testing. Test cases are designed by ISTQB-certified analysts, and every defect gets a root cause classification, so after a few sprints it is clear where most errors originate and what to improve in the development process.

We take over the role of program test manager: one test strategy for all workstreams, a shared tool, shared entry and exit criteria, and a weekly readiness report based on data rather than declarations. Acceptance testing is run by claims adjusters with our methodological support.

Key elements of the solution:

  • One test strategy for the program and plans per workstream
  • A traceability matrix of processes, requirements and tests
  • A readiness report with objective indicators
  • A defect triage process with the vendor

Team and roles

RoleCountResponsibility
Test manager (ISTQB Advanced)1test strategy, entry and exit criteria, quality reporting
QA lead1organizing testers' work, test case reviews, defect metrics
Test analyst (ISTQB)4designing and executing test cases, reporting defects
Business analyst1requirements, processes, acceptance criteria
Product owner and domain experts (client side)as neededpriorities, business decisions, acceptance

Phased schedule

PhaseWeeksDeliverable
1. Analysis and test strategy1–5test strategy, risk matrix, environment plan
2. Test case design6–12test case repository with traceability
3. System and integration testing13–25daily reports, defect register
4. Acceptance testing (UAT) with the business26–32UAT protocols, exit criteria
5. Closure report and handover33–36quality report, recommendations

Technology stack

Jira Xray, Confluence, Power BI, SQL.

Risks and how we mitigate them

RiskHow we mitigate it
Dependence on an external provider and its deadlinesearly agreement on API contracts, a stub environment, a weekly review of dependencies
Diverging stakeholder expectationsstakeholder map, a shared definition of success, a monthly steering committee
Unavailable or unstable test environmentsan environment booking schedule, virtualization of external services (mocks), a daily environment smoke test
Scope creep during the projecta backlog prioritized with MoSCoW, every change goes through the committee with an estimate of its impact on the deadline

Measurable goals and KPIs

The values below are goals that we set with the client after a baseline measurement in the first phase.

KPITargetHow it is measured
Defect detection effectiveness (DDE)≥ 90%defects found in testing / all defects within 90 days
Critical defects found after release0 critical defects in the first 30 daysproduction incident register
E2E processes covered by tests before go-live100% of critical processestest catalog

Lessons learned and good practices

A data-based readiness report is the most effective tool for a steering committee, because it ends the “we feel it's ready” discussions. Daily defect triage with the vendor shortens fix times. Traceability from requirements to tests is cheap when you build it from day one, and very expensive when you reconstruct it before an audit.

Why B2B.net

We combine two models: we provide individual specialists and whole teams (time and materials, team leasing), and when a client prefers to hand over responsibility for the result, we work at a fixed price for a defined scope. We have access to a large network of engineers in six cities, SAP Center of Expertise competencies, and experience with ISO 27001, DORA and NIS2 requirements. If someone leaves the team, a replacement is in place within 5 business days.

Next step

If you recognize these problems in your own organization, let's start with a short diagnosis: one workshop with your team and a written recommendation. Write to office@b2bnetwork.pl.

What would this look like for you?

Book a 30-minute call. We will prepare a plan for the first weeks and a team matched to your system.

Let's talk

B2Bnetwork · B2B.net S.A. · accredited exam center. We describe clients by industry and scale, without names.

More projects: Insurance